Kitchen Appliance Eco-Coating Upgrade
CASE STUDY · 2024

Kitchen Appliance Eco-Coating Upgrade

Eco-UpgradeRTOKitchen Appliance
Request Similar Solution Back to Cases

Project Background

The client is a top-5 kitchen appliance brand in Indonesia. Their existing range hood and water heater coating lines couldn't meet Indonesia's tightened 2024 emission standards (≤5 mg/m³). Urgent environmental upgrade was required.

The Challenge

5 coating lines running simultaneously — high airflow (28,000 m³/h), low concentration (200-400 mg/m³). Traditional activated carbon would mean high running cost; pure RTO has minimum concentration requirements.

MUSI's Solution

MUSI recommended a zeolite rotor concentrator + RTO combined solution: 5 lines' exhaust collected centrally → zeolite rotor concentrates 12x (raises concentration to 2,400-4,800 mg/m³) → 3-chamber RTO incineration (DRE ≥98%). Best total cost of ownership.

Equipment Configuration

Exhaust source5 coating lines
Total airflow30,000 m³/h
Inlet concentration200-400 mg/m³
Outlet concentration≤5 mg/m³ (meets new standard)
Zeolite rotor3.5 m diameter, 12-15x concentration
RTO type3-chamber regenerative thermal oxidizer
Heat recovery≥95%
Self-sustained≥1,500 mg/m³ no auxiliary fuel needed

Implementation

90-day delivery, 25 days on-site installation. Client factory was in busy production season — MUSI worked nights and connected piping on weekends to minimize impact.

Results

Post-upgrade emissions stable at 3-4 mg/m³, well below the 5 mg/m³ standard. Annual operating cost $54K USD lower than the alternative activated carbon solution — payback on the additional zeolite rotor investment in 3 years.

Client Feedback

"The new emission standards came suddenly. MUSI delivered the optimal solution in record time, helping us pass environmental inspection smoothly."
— Project Manager, Client Side