Vertical Powder Coating for Aluminum Profiles
CASE STUDY · 2023

Case Study: Aluminium Profile Vertical Coating Line

  • IndustryAluminum Profiles
  • Year2023
  • LocationUnited Arab Emirates
  • ScaleWorkpieces up to 7 m, 600,000 m/year
Vertical BoothOutdoor WeatherableArchitectural
Request Similar Solution Back to Cases

Project Background

The client is one of the largest aluminum profile manufacturers in the UAE, supplying door & window factories and curtain wall contractors across the Gulf region. They demanded coatings with 25-year outdoor service life. Their previous vertical manual spray was inefficient and produced inconsistent thickness.

The Challenge

Architectural aluminum profiles run 4-7 m long (max 6.8 m), requiring tall booths and special conveyance. Profile cross-sections are complex (multi-cavity, decorative patterns) — standard booths produce missed spots or powder buildup.

MUSI's Solution

MUSI engineered a 9-meter-tall vertical powder coating system: workpieces hang vertically through the booth with 14 circumferentially-mounted spray guns + reciprocating motion ensuring uniform coating on all faces. Outdoor-grade polyester powder paired with precise oven control delivers 2,000+ hour salt spray performance.

Equipment Configuration

Booth9 m vertical powder coating booth
Workpiece length1.5-7 m
Max cross-section300×300 mm
Spray guns14 (circumferential + vertical reciprocator)
Conveyor speed0.8-2.5 m/min
Drying oven9 m bridge gas oven, 200-220 °C
Throughput400-500 m²/hour
Powder utilization≥97%

Implementation

95-day project from site survey to production launch. Construction challenges: ceiling raise (partial roof opening) and heavy vertical booth lifting. MUSI worked closely with the client's contractors to complete safely and on time.

Results

Daily capacity rose from 1,800 m to 4,500 m — a 150% increase. Salt spray testing reached 2,200 hours flawless. The client won orders from premium door & window brands and grew 40% YoY. Now a leading supplier in the UAE.

Client Feedback

"We evaluated several suppliers before choosing MUSI. Their vertical booth technology is the most mature solution we found. Over a year in operation now, no significant issues."
— Project Manager, Client Side

Get a Similar Solution

If your industry and requirements match this case, contact MUSI to schedule a free consultation. We'll design an optimal solution based on your specific workpieces, capacity, and facility.