Metal Tube Automatic Coating Line
CASE STUDY · 2023

Metal Tube Automatic Coating Line

  • IndustryMetal Hardware
  • Year2023
  • LocationPakistan
  • ScaleTube diameter 16-150 mm
TubingContinuous CoatingPowder
Request Similar Solution Back to Cases

Project Background

The client is a major steel and stainless steel tube manufacturer in Pakistan, with annual production 100,000 tons. They needed a coating line for premium tubing (outdoor handrails, fitness equipment tubing).

The Challenge

Tubes are long (4-6 m) — traditional spray methods struggle with uniformity. Tube diameters span 16-150 mm — line must handle full range.

MUSI's Solution

MUSI designed a tube-specific rotating conveyor + circumferential spray solution: tubes rotate on V-rollers while passing through 8 circumferentially-mounted powder spray guns — uniform coating around tube circumference. Auto-adjusts to different tube diameters.

Equipment Configuration

Line typeTube rotating continuous coating
Tube diameter16-150 mm auto-adapting
Tube length4-6 m
ConveyanceV-roller rotating conveyor
Spray gun layoutCircumferential, 8 guns
Conveyor speed5-15 m/min
Capacity150-300 m/hour
Film uniformity±10%

Implementation

65-day delivery. Auto-adapting to different tube diameters was the challenge — MUSI designed a pneumatic V-roller frame that auto-adjusts in 30 seconds.

Results

Line capacity 250 m/hour — 25% above client expectations. Tube surface visual pass rate 99%+.

Client Feedback

"Tube coating is a niche market — finding the right supplier is hard. MUSI's specialized solution made our line investment worthwhile."
— Project Manager, Client Side

Get a Similar Solution

If your industry and requirements match this case, contact MUSI to schedule a free consultation. We'll design an optimal solution based on your specific workpieces, capacity, and facility.