Hardware Robotic Flexible Coating Line
CASE STUDY · 2024

Case Study: Hardware Robotic Flexible Coating Line

  • IndustryMetal Hardware
  • Year2024
  • LocationIndia
  • Scale12 robots, 20,000 pcs/day
RoboticFlexible ProductionMulti-Variety
Request Similar Solution Back to Cases

Summary

A robotic flexible coating line for a lock and metal hardware manufacturer in Pune, India, running 200+ SKUs with automatic program changeover in under 3 minutes and 20,000–25,000 pieces per day. Twelve ABB robots (6 spraying, 4 loading and unloading, 2 inspection) work with Cognex vision and 2-axis part manipulators, and the line is order-driven through MES integration. Film uniformity is held to ±3 μm, first-pass rate rose from 86% to 99.6%, and manning fell from 32 to 6. Figures as reported after commissioning in 2024.

Project Background

The client is India's leading lock and metal hardware manufacturer, producing 200+ SKUs. Their existing manual coating line had high labor costs and inconsistent quality. They engaged MUSI to bring robotic flexible automation to their facility in Pune.

The Challenge

Lock products span 200+ SKUs with 20-30 product changeovers per day. Traditional fixed-program automatic lines lacked the flexibility needed. Lock structures are complex (cores, handles, decorative parts), with many recessed coating areas.

MUSI's Solution

MUSI designed a robotic flexible coating solution: ABB IRB1410 robot for vision-guided loading, 6 ABB IRB52 spray robots working in coordination, paired with 2-axis workpiece manipulators for full-coverage coating. Full MES integration enables order-driven program selection.

Equipment Configuration

Robots12 ABB units (6 spray + 4 load/unload + 2 inspection)
Vision systemCognex In-Sight 8000 series
Product SKUs200+ lock products
Changeover≤3 minutes (auto program switch)
Daily capacity20,000-25,000 pcs
Film uniformity±3 μm
ManningOriginally 32 people, now 6
MES integrationOrder-driven flexible production

Implementation

4-6 month timeline: 30 days design, 90 days manufacturing, 20 days installation, 40 days robot offline programming + commissioning. Robot commissioning was the critical phase — MUSI's senior engineers worked alongside ABB India's tech team.

Results

Labor reduced 81%, per-unit cost down 42%, film pass rate from 86% to 99.6%. The transformation moved the client from 'traditional hardware factory' to 'smart manufacturing operation' — recognized by India's Ministry of Heavy Industries as a smart manufacturing demonstration project.

Client Feedback

"The investment was significant, but the returns far exceeded expectations. Robots are more stable and precise than manual operators, and we no longer worry about labor shortages."
— Project Manager, Client Side

Selection logic: why this configuration

Robots were chosen over a fixed-program reciprocator line because locks change 20–30 times a day and each SKU has recessed areas that a reciprocator cannot reach. Vision-guided loading replaced dedicated fixtures so that changeover became a program call rather than a tooling change. Six spray robots in coordinated pairs, rather than three larger cells, keep the takt when one cell is being cleaned.

Scope of supply and key components

ItemSpecificationNotes
Spray robots6 × ABB, paired, with 2-axis part manipulatorsOffline programming, 200+ programs
Handling robots4 × ABB load/unload, 2 × inspectionCognex In-Sight vision guidance
Spray boothsRobot cells with overspray extraction
CuringOven matched to lock substrates
MES integrationOrder-driven program selection, data logging

Key components

Key components are available from international brands, configurable per customer specification, so that spare parts can be sourced locally over the life of the line. Brand names below are the usual options for this type of equipment; the brands actually fitted are fixed in the contract specification.

ComponentBrands available on request
Painting robotsABB IRB 5500, FANUC P-350iA, Yaskawa MOTOMAN MPX series, KUKA, Kawasaki
Automatic liquid guns, pumps and 2K proportionersInternational tier-one spray gun, pump and 2K proportioner brands
PLC and HMISiemens SIMATIC S7-1500, Mitsubishi Electric MELSEC iQ-R, Schneider Electric Modicon, OMRON NX, Rockwell Automation Allen-Bradley
Variable-frequency drivesABB ACS580, Siemens SINAMICS G120, Danfoss VLT, Schneider Electric Altivar, Yaskawa, Mitsubishi Electric
Booth ceiling and intake filter mediaFreudenberg Viledon, AAF SureStop, Camfil, MANN+HUMMEL
Sensors and temperature controllersSICK, Pepperl+Fuchs, OMRON E5CC, Honeywell UDC, Yokogawa UT, ifm, KEYENCE
PneumaticsFesto, SMC, Parker Hannifin, Norgren
Oven and dryer gas burnersRiello RS series, Weishaupt monarch WM-G, Baltur TBG, Honeywell Maxon OVENPAK, Eclipse

Not included in the scope of supply

  • Civil works, foundations and pits
  • Building services up to the battery limit: power supply, gas, compressed air, water and drainage
  • Local permits, emission approvals and third-party inspections
  • Paint or powder supply, unless stated in the contract

Services included with every line: engineering design, manufacturing, shipping documentation, installation supervision, commissioning, operator training, warranty and spare parts.

Typical programme

The durations below are typical for equipment of this class and are given for planning; they are not the recorded schedule of this project. A complete line usually runs 90–180 days from contract to acceptance, a single unit 30–60 days.

StageTypical durationWhat happens
Site survey and workpiece review5–10 daysRemote review of drawings and photos, or an engineer visit
Layout and detail design15–30 daysLayout drawing, utilities list and specification sign-off
Manufacturing45–90 daysBooths, ovens, conveyor, pretreatment and controls built and pre-assembled at the works
Shipping20–45 daysSea freight; equipment shipped in sections for on-site assembly
Installation15–40 daysMUSI supervision with the client's installation crew or MUSI crew
Commissioning, training and acceptance7–15 daysTrial runs on the client's parts, operator training, acceptance record

Results: before and after

Figures are those published on this page; measurement party, sample size, test date and method are not on record here and are left blank rather than estimated.

MetricBeforeAfterChangeMeasured bySingle / averageSamplesTest dateMethod / instrument
First-pass film rate86%99.6%+13.6 pts
Manning per shift326−81%
Cost per unitbaseline−42%−42%
Changeovermanual≤3 min—

Applicability and limits

The 3-minute changeover and 20,000-piece daily rate apply to small hardware with a stable SKU library and offline-programmed robot paths. New SKUs still need programming and trial parts before they run at rate, and plants without a local robot service partner should plan for training of their own maintenance team.

Results shown in this case study reflect the stated operating conditions and should not be interpreted as guaranteed performance under different feed, production, environmental, or site conditions.

After-sales and spare parts

Warranty on a MUSI coating line runs from acceptance: 12 months on the complete line excluding consumables, 36 months on critical components such as motors, drives and the PLC, and 60 months on structural parts such as steel structure, ducting and oven bodies. Failures within warranty, excluding misuse, are repaired free of charge.

Support starts remotely: the service line is staffed around the clock, a preliminary diagnosis with recommendations is given within 2 hours, and where a site visit is needed an engineer reaches any major city within 72 hours. A spare-parts inventory is held at the Changzhou headquarters with same-day shipping, and customers can keep a dedicated parts stock at MUSI for emergencies. Details are on the after-sales service page.

FAQ

When does a robotic line pay off over a reciprocator line? When SKU count is high and changeovers are frequent, or when part geometry has recesses that fixed guns miss. This client changed products 20–30 times a day, which is where robots earn their cost.

How is the 3-minute changeover achieved? Each SKU has a stored robot program and vision reference. The MES sends the order, the robots load the program and the vision system confirms part position, so no fixtures are swapped.

How many people run the line? Six per shift after the project, down from 32 on the manual line: robot operators, a line supervisor and quality staff.

Who programmed the robots? MUSI engineers wrote and tuned the programs offline and commissioned them with ABB India's technical team during the 40-day programming and commissioning phase.

What was the overall project timeline? Four to six months: 30 days design, 90 days manufacturing, 20 days installation and 40 days robot programming and commissioning.

Next step: a configuration proposal for a similar line

If your parts, volumes or plant conditions are close to this project, MUSI can return a line configuration and layout proposal. To prepare it we need four things:

  • Photos and dimensions of the workpieces, with weight and material
  • Required output (pieces per hour or per day, and shifts)
  • Number of colours and how often colour changes are needed
  • Available floor space and ceiling height, with the utilities on site

Message us on WhatsApp with these details, or use the quotation form.

Provided by Lin Cong, Technical Director, MUSI Technology · Published 2026-05-02 · Updated 2026-09-30 · Last technical review: 2026-09-30

Q

Questions buyers ask before ordering

quotation · price · lead time · installation · warranty

What information do you need to prepare a quotation?

Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.

How much does this equipment cost?

Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our complete coating line cost guide; a configured quotation is prepared from your part data. Published indicative ex-works ranges: a complete powder coating line is roughly USD 75,000–230,000 semi-automatic, USD 200,000–600,000 for a standard automatic line and USD 600,000–2,000,000 for a high-throughput automated plant.

What is the lead time?

Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.

Do you install and train operators overseas?

Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.

What warranty and after-sales support are included?

12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.

Can the environmental equipment be supplied with the line?

Yes. VOC treatment (RTO, RCO, activated carbon, zeolite rotor), dust collection and paint wastewater treatment are supplied with the coating line under one contract; MUSI has equipped 50+ coating facilities whose projects all passed local environmental compliance reviews.