Case Study: Furniture Industry VOCs Treatment Project
Summary
An activated-carbon adsorption and catalytic oxidation (RCO) system for a large solid-wood furniture factory in Malaysia, treating 25,000 m³/h of exhaust from five dispersed spray booths whose concentration swings from 50 mg/m³ to 800 mg/m³. Twenty-four honeycomb carbon beds adsorb at ≥92% efficiency, hot air at 160 °C desorbs them in turn, and a 5,000 m³/h RCO with a platinum-palladium catalyst oxidises the concentrated stream. Stack concentration holds at 18–22 mg/m³ against a 30 mg/m³ limit and annual operating cost is USD 46,000 below the RTO alternative, as reported after commissioning in 2024.
Project Background
The client is a large solid wood furniture factory in Malaysia, with annual revenue of $70 M USD. Local environmental regulations in 2024 required furniture industry VOCs emissions ≤30 mg/m³. The client had no VOCs treatment equipment and urgent installation was required.
The Challenge
Furniture factory spray stations are dispersed (5 separate spray booths), exhaust concentration fluctuates widely (50 mg/m³ during intermittent production, 800 mg/m³ during peak). Solution must adapt flexibly.
MUSI's Solution
MUSI proposed activated carbon adsorption + catalytic combustion (RCO) combination: 5 booths' exhaust collected centrally → honeycomb activated carbon adsorption (24 beds) → periodic hot air desorption → RCO catalytic combustion. 40% lower investment than RTO.
Equipment Configuration
| Total exhaust | 25,000 m³/h |
|---|---|
| Adsorption | Honeycomb activated carbon (24 beds) |
| Adsorption efficiency | ≥92% |
| Desorption | Hot air (160 °C) |
| RCO capacity | 5,000 m³/h (desorbed gas) |
| Catalyst | Pt/Pd noble metal |
| Outlet concentration | ≤25 mg/m³ |
| Carbon life | 12-18 months |
Equipment used on this line
- Automatic spray coating lines — overhead chain, floor belt and robotic flexible lines
- VOCs and environmental equipment — RTO, RCO, activated carbon, zeolite rotor and wastewater treatment
Implementation
70-day delivery. The 5 spray booth duct connections were the challenge (varying distances and elevations).
Results
After commissioning, the project passed environmental authority validation. Emission concentration stable 18-22 mg/m³. Annual operating cost $46K USD lower than the RTO alternative.
Client Feedback
"We used to think environmental treatment was just 'burning money'. MUSI helped us find the most suitable solution — letting us focus on growth without distractions."
— Project Manager, Client Side
Selection logic: why this configuration
Carbon adsorption with RCO was chosen over an RTO because furniture spraying is intermittent and the exhaust concentration swings tenfold; carbon beds level the load and the small RCO oxidises a steady desorbed stream, at about 40% lower investment. An RCO was preferred to venting the desorbed gas to a burner because the platinum-palladium catalyst oxidises at a lower temperature and lower gas use. Twenty-four beds were specified so that beds can be desorbed in rotation without stopping any booth.
Scope of supply and key components
| Item | Specification | Notes |
|---|---|---|
| Exhaust collection | 5 spray booths, 25,000 m³/h | Ducting over varying distances and levels |
| Adsorption | 24 honeycomb activated-carbon beds, ≥92% | Carbon life 12–18 months |
| Desorption | Hot air, 160 °C, in rotation | |
| RCO | 5,000 m³/h, Pt/Pd catalyst | Outlet ≤25 mg/m³ design |
| Controls | PLC with bed sequencing and monitoring |
Key components
Key components are available from international brands, configurable per customer specification, so that spare parts can be sourced locally over the life of the line. Brand names below are the usual options for this type of equipment; the brands actually fitted are fixed in the contract specification.
| Component | Brands available on request |
|---|---|
| Oven and dryer gas burners | Riello RS series, Weishaupt monarch WM-G, Baltur TBG, Honeywell Maxon OVENPAK, Eclipse |
| PLC and HMI | Siemens SIMATIC S7-1500, Mitsubishi Electric MELSEC iQ-R, Schneider Electric Modicon, OMRON NX, Rockwell Automation Allen-Bradley |
| Variable-frequency drives | ABB ACS580, Siemens SINAMICS G120, Danfoss VLT, Schneider Electric Altivar, Yaskawa, Mitsubishi Electric |
| Sensors and temperature controllers | SICK, Pepperl+Fuchs, OMRON E5CC, Honeywell UDC, Yokogawa UT, ifm, KEYENCE |
| Low-voltage switchgear and relays | Schneider Electric TeSys, ABB AF, Siemens SIRIUS, OMRON, Eaton |
| RTO ceramic media and burners | Lantec MLM, Honeywell Maxon line burners, Riello RS, Eclipse |
Not included in the scope of supply
- Civil works, foundations and pits
- Building services up to the battery limit: power supply, gas, compressed air, water and drainage
- Local permits, emission approvals and third-party inspections
- Paint or powder supply, unless stated in the contract
- Replacement activated carbon after the first fill
Services included with every line: engineering design, manufacturing, shipping documentation, installation supervision, commissioning, operator training, warranty and spare parts.
Typical programme
The durations below are typical for equipment of this class and are given for planning; they are not the recorded schedule of this project. A complete line usually runs 90–180 days from contract to acceptance, a single unit 30–60 days.
| Stage | Typical duration | What happens |
|---|---|---|
| Data review and sizing | 3–7 days | Exhaust data or part drawings reviewed remotely |
| Design | 10–20 days | General arrangement and connection points |
| Manufacturing | 30–60 days | Unit built and factory tested |
| Shipping | 20–45 days | Sea freight |
| Installation and connection | 7–25 days | Ducting, gas or utilities connected on site |
| Commissioning and acceptance | 5–10 days | Performance run and acceptance record |
Results: before and after
Figures are those published on this page; measurement party, sample size, test date and method are not on record here and are left blank rather than estimated.
| Metric | Before | After | Change | Measured by | Single / average | Samples | Test date | Method / instrument |
|---|---|---|---|---|---|---|---|---|
| Stack concentration | no treatment | 18–22 mg/m³ (limit 30) | compliant | |||||
| Annual operating cost | RTO alternative | USD 46,000 lower | −USD 46,000/yr |
Applicability and limits
The 18–22 mg/m³ result applies to solvent-borne wood-finishing exhaust with the stated swing in concentration. Streams with high dust or sticky resin load need better pre-filtration to protect the carbon, continuous high-concentration lines are usually treated by an RTO instead, and carbon life depends on the actual solvent load.
Results shown in this case study reflect the stated operating conditions and should not be interpreted as guaranteed performance under different feed, production, environmental, or site conditions.
After-sales and spare parts
Warranty on a MUSI coating line runs from acceptance: 12 months on the complete line excluding consumables, 36 months on critical components such as motors, drives and the PLC, and 60 months on structural parts such as steel structure, ducting and oven bodies. Failures within warranty, excluding misuse, are repaired free of charge.
Support starts remotely: the service line is staffed around the clock, a preliminary diagnosis with recommendations is given within 2 hours, and where a site visit is needed an engineer reaches any major city within 72 hours. A spare-parts inventory is held at the Changzhou headquarters with same-day shipping, and customers can keep a dedicated parts stock at MUSI for emergencies. Details are on the after-sales service page.
FAQ
RTO or carbon plus RCO for a furniture factory? Carbon with RCO when spraying is intermittent and concentration swings widely, as with this plant's five booths; an RTO when the line runs continuously at a steady, higher concentration.
What emission level does the system reach? Stable at 18–22 mg/m³ at the stack against the 30 mg/m³ limit, validated by the environmental authority after commissioning.
How often is the carbon replaced? Every 12–18 months at this plant's load; the beds are desorbed with hot air in rotation between replacements.
Why 24 carbon beds? So that some beds are always adsorbing while others are desorbed, with no booth taken off line during the cycle.
How were five separate booths connected? Through a collection duct system sized for the different distances and elevations, which was the main installation task in the 70-day delivery.
Next step: a configuration proposal for a similar line
If your parts, volumes or plant conditions are close to this project, MUSI can return a line configuration and layout proposal. To prepare it we need four things:
- Photos and dimensions of the workpieces, with weight and material
- Required output (pieces per hour or per day, and shifts)
- Number of colours and how often colour changes are needed
- Available floor space and ceiling height, with the utilities on site
Message us on WhatsApp with these details, or use the quotation form.
Provided by Lin Cong, Technical Director, MUSI Technology · Published 2026-05-02 · Updated 2026-09-30 · Last technical review: 2026-09-30
QQuestions buyers ask before ordering
quotation · price · lead time · installation · warranty
What information do you need to prepare a quotation?
Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.
How much does this equipment cost?
Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our complete coating line cost guide; a configured quotation is prepared from your part data. Published indicative ex-works ranges: a complete powder coating line is roughly USD 75,000–230,000 semi-automatic, USD 200,000–600,000 for a standard automatic line and USD 600,000–2,000,000 for a high-throughput automated plant.
What is the lead time?
Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.
Do you install and train operators overseas?
Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.
What warranty and after-sales support are included?
12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.
Can the environmental equipment be supplied with the line?
Yes. VOC treatment (RTO, RCO, activated carbon, zeolite rotor), dust collection and paint wastewater treatment are supplied with the coating line under one contract; MUSI has equipped 50+ coating facilities whose projects all passed local environmental compliance reviews.
Get a Similar Solution
If your industry and requirements match this case, contact MUSI to schedule a free consultation. We'll design an optimal solution based on your specific workpieces, capacity, and facility.