Yellow overhead conveyor tracks on rows of white support columns across a coating workshop
CASE STUDY · 2026

Case Study: Machinery & Agricultural Parts Coating Line, Jiangsu

  • ClientConstruction and agricultural machinery parts maker
  • IndustryHeavy Machinery
  • Year2026
  • LocationChina
  • ScaleConstruction machinery and agricultural equipment parts
Construction MachineryAgricultural EquipmentCoating Line
Request Similar Solution Back to Cases

Summary

A machinery-scale coating line for a maker of construction machinery and agricultural equipment parts in Jiangsu, with pretreatment for heavy steel, spray booths, a curing oven with a platform-mounted burner sized for thick plate, a conveyor system and exhaust treatment. Oven heating and conveyor speed were matched so thick sections reach full cure temperature through the metal, not only at the surface. The line is in regular production in 2026.

Project Background

The client makes parts for construction machinery and agricultural equipment in Jiangsu.

The Challenge

Machinery for construction sites and farms works outdoors, in mud, water and fertiliser. The finish has to protect heavy steel parts for years, and the line has to handle thick plate that takes longer to heat through in the oven.

MUSI's Solution

MUSI supplied a machinery-scale line with pretreatment, spray booths and a curing oven sized for heavy plate. The oven heating and conveyor speed were matched so thick parts reach full cure temperature, not just the surface.

Curing oven burner mounted on a steel platform
Curing oven burner mounted on a steel platform

Equipment Scope

  • Pretreatment line for heavy steel parts
  • Spray booths
  • Curing oven with platform-mounted burner
  • Conveyor system
  • Exhaust treatment

Results

The line is in regular production for the client’s construction and agricultural machinery parts.

Selection logic: why this configuration

The oven was sized for heat-through of thick plate rather than for surface temperature because agricultural and construction parts fail in service when the coating on heavy sections is under-cured. A platform-mounted burner was specified for maintenance access, and conveyor speed was fixed from the heaviest part's heat-up time rather than from the booth.

Scope of supply and key components

ItemSpecificationNotes
PretreatmentFor heavy steel parts
Spray boothsSized for machinery parts
Curing ovenPlatform-mounted burner, sized for thick plate
ConveyorOverhead conveyor
Exhaust treatmentBooth and oven exhaust

Key components

Key components are available from international brands, configurable per customer specification, so that spare parts can be sourced locally over the life of the line. Brand names below are the usual options for this type of equipment; the brands actually fitted are fixed in the contract specification.

ComponentBrands available on request
Oven and dryer gas burnersRiello RS series, Weishaupt monarch WM-G, Baltur TBG, Honeywell Maxon OVENPAK, Eclipse
Automatic liquid guns, pumps and 2K proportionersInternational tier-one spray gun, pump and 2K proportioner brands
Automatic powder guns and powder feedInternational tier-one powder spray gun brands
PLC and HMISiemens SIMATIC S7-1500, Mitsubishi Electric MELSEC iQ-R, Schneider Electric Modicon, OMRON NX, Rockwell Automation Allen-Bradley
Variable-frequency drivesABB ACS580, Siemens SINAMICS G120, Danfoss VLT, Schneider Electric Altivar, Yaskawa, Mitsubishi Electric
Conveyor gear motorsSEW-EURODRIVE, NORD DRIVESYSTEMS, Bonfiglioli, Siemens, Sumitomo Drive Technologies
Pretreatment pumps and chemistryGrundfos CR, KSB Etanorm, Xylem; Henkel BONDERITE, Chemetall Gardobond, PPG Zircobond, Nippon Paint
Sensors and temperature controllersSICK, Pepperl+Fuchs, OMRON E5CC, Honeywell UDC, Yokogawa UT, ifm, KEYENCE

Not included in the scope of supply

  • Civil works, foundations and pits
  • Building services up to the battery limit: power supply, gas, compressed air, water and drainage
  • Local permits, emission approvals and third-party inspections
  • Paint or powder supply, unless stated in the contract

Services included with every line: engineering design, manufacturing, shipping documentation, installation supervision, commissioning, operator training, warranty and spare parts.

Typical programme

The durations below are typical for equipment of this class and are given for planning; they are not the recorded schedule of this project. A complete line usually runs 90–180 days from contract to acceptance, a single unit 30–60 days.

StageTypical durationWhat happens
Site survey and workpiece review5–10 daysRemote review of drawings and photos, or an engineer visit
Layout and detail design15–30 daysLayout drawing, utilities list and specification sign-off
Manufacturing45–90 daysBooths, ovens, conveyor, pretreatment and controls built and pre-assembled at the works
Shipping20–45 daysSea freight; equipment shipped in sections for on-site assembly
Installation15–40 daysMUSI supervision with the client's installation crew or MUSI crew
Commissioning, training and acceptance7–15 daysTrial runs on the client's parts, operator training, acceptance record

Applicability and limits

The oven sizing here is specific to the plate thickness of this client's parts; thinner fabrications cure faster and lighter ovens suffice. Parts that work in fertiliser or salt environments may also need a specified primer system, which is set by the coating supplier's data sheet.

Results shown in this case study reflect the stated operating conditions and should not be interpreted as guaranteed performance under different feed, production, environmental, or site conditions.

After-sales and spare parts

Warranty on a MUSI coating line runs from acceptance: 12 months on the complete line excluding consumables, 36 months on critical components such as motors, drives and the PLC, and 60 months on structural parts such as steel structure, ducting and oven bodies. Failures within warranty, excluding misuse, are repaired free of charge.

Support starts remotely: the service line is staffed around the clock, a preliminary diagnosis with recommendations is given within 2 hours, and where a site visit is needed an engineer reaches any major city within 72 hours. A spare-parts inventory is held at the Changzhou headquarters with same-day shipping, and customers can keep a dedicated parts stock at MUSI for emergencies. Details are on the after-sales service page.

FAQ

How do you make sure thick steel parts cure fully? By sizing the oven and conveyor speed from the time the heaviest section takes to reach cure temperature, checked with thermocouples on the part, not the oven air.

What protection do farm and construction parts need? A coating system rated for mud, water and fertiliser exposure over years; the line applies whatever system the specification names, with pretreatment sized for heavy steel.

Why mount the burner on a platform? For safe access to the burner, gas train and controls during maintenance without stopping the conveyor below.

Can the line take both construction and agricultural parts? Yes; both families are heavy welded steel with similar coating requirements and share the pretreatment, booths and oven.

Is the line running? Yes, in regular production for the client's machinery parts.

Next step: a configuration proposal for a similar line

If your parts, volumes or plant conditions are close to this project, MUSI can return a line configuration and layout proposal. To prepare it we need four things:

  • Photos and dimensions of the workpieces, with weight and material
  • Required output (pieces per hour or per day, and shifts)
  • Number of colours and how often colour changes are needed
  • Available floor space and ceiling height, with the utilities on site

Message us on WhatsApp with these details, or use the quotation form.

Published 2026-09-26 · Updated 2026-09-30 · Last technical review: 2026-09-30

Q

Questions buyers ask before ordering

quotation · price · lead time · installation · warranty

What information do you need to prepare a quotation?

Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.

How much does this equipment cost?

Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our complete coating line cost guide; a configured quotation is prepared from your part data. Published indicative ex-works ranges: a complete powder coating line is roughly USD 75,000–230,000 semi-automatic, USD 200,000–600,000 for a standard automatic line and USD 600,000–2,000,000 for a high-throughput automated plant.

What is the lead time?

Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.

Do you install and train operators overseas?

Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.

What warranty and after-sales support are included?

12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.

Can the environmental equipment be supplied with the line?

Yes. VOC treatment (RTO, RCO, activated carbon, zeolite rotor), dust collection and paint wastewater treatment are supplied with the coating line under one contract; MUSI has equipped 50+ coating facilities whose projects all passed local environmental compliance reviews.

Request a configured quotationWhatsApp +86 181 5173 1332 · lin@coating-spray.com

Get a Similar Solution

If your industry and requirements match this case, contact MUSI to schedule a free consultation. We'll design an optimal solution based on your specific workpieces, capacity, and facility.

Provided by Lin Cong, Technical Director, MUSI Technology