Telescopic spray booth on ground rails outside a workshop under a gantry crane, with steel structures laid out for painting
CASE STUDY · 2024

Case Study: 20 m Telescopic Spray Booth for a Bridge Girder Fabricator, India

  • ClientSteel bridge girder fabricator (name withheld)
  • IndustryBridge Girders
  • Year2024
  • LocationIndia
  • Scale20 x 10 x 4 m dry-filter telescopic booth
South AsiaBridge GirdersOutdoor BoothIndia
Request Similar Solution Back to Cases

Summary

ObjectPlate girders and cross frames up to 20 m for a Steel bridge girder fabricator in India
Equipment20 x 10 x 4 m dry-filter telescopic booth
Operating conditionscrane-handled batch painting, dry filter wall: labyrinth paper filters plus glass-fibre bags, cross-draft 0.3 m/s or more
ResultGirders painted on stands under the gantry without a building
Sourceproject specification and commissioning scope; client name withheld at the client's request

Project Background

An Indian fabricator of plate girders for road and rail bridges painted girders to a multi-coat system specified by the client's consultant. Girders of 20 m were laid out in the yard under a gantry crane; painting in the open was stopped by the state pollution rules, and no building was available for a fixed booth.

Pain Points Before the Project

  • No indoor bay long enough for 20 m girders
  • Open-air painting no longer permitted
  • Dust from the yard settling on wet paint
  • Painting stopped in rain and wind

Why This Configuration Was Chosen

  • A 20 x 10 x 4 m telescopic booth installed outdoors on rails under the gantry crane, with the fixed end, fan and stack on a concrete pad
  • UV-stabilised flame-retardant fabric and a 75 kW fan give an enclosed, ventilated space independent of the weather
  • Dry filtration plus carbon and UV treatment met the state limit at the yard's painting schedule
Telescopic mobile spray booth fully extended over long steel beams inside a fabrication workshop, with lighting rows and white fabric walls
Telescopic mobile spray booth fully extended over long steel beams inside a fabrication workshop, with lighting rows and white fabric walls

Scope of Supply

Telescopic enclosure20 x 10 x 4 m internal (retracted about 3 x 10.7 m); Q235 frames 50 x 70 x 2 mm, flame-retardant PVC fabric
Drive and safety2 x 1.5 kW explosion-proof geared motors, 8-10 m/min; interlocked drives, double limit switches, rail sweeper, jog control
Lighting60 explosion-proof LED units, 18 W each, 300 lux or more
Paint mist captureDry filter wall: labyrinth paper filters plus glass-fibre bags, 98% or more mist capture
Exhaust treatmentActivated carbon boxes plus UV photo-oxidation unit, 50,000 m3/h class
Fan, duct and stack75 kW centrifugal fan, 54,000-79,400 m3/h, 15 m stack
ControlTwo-station control cabinet, VFD on exhaust fan, emergency stop, audible-visual travel alarm
Installed powerabout 109 kW installed

Component brands. Key components are sourced from international first-tier brands at the client's choice; the table lists the options offered on this project.

ComponentBrand options
Exhaust fanNicotra Gebhardt, Kruger, Systemair
Geared drive motorsSEW-Eurodrive, NORD, Bonfiglioli
Explosion-proof lightingEaton Crouse-Hinds, R. STAHL, ABB
Low-voltage switchgearSchneider Electric, Siemens, ABB
Variable frequency driveABB, Danfoss, Siemens
PLC (RCO control)Siemens, Mitsubishi Electric, Omron
Filter mediaAndreae Filters, Freudenberg Viledon, Camfil
Activated carbonCalgon Carbon, Jacobi Carbons, Cabot Norit
Oxidation catalystBASF, Johnson Matthey, Clariant
Flame-retardant fabricSerge Ferrari, Sioen, Mehler Texnologies
Flexible cablesLAPP, Nexans, Prysmian
Airless spray units (client side)Graco, WIWA, WAGNER

Not included: rail levelling and civil foundations, site lifting, third-party emission testing, workpiece stands unless ordered, and the drying room where forced cure is required.

Programme

Typical programme for this booth class; the dates for each project are fixed in the contract.

StageTypical duration
Site survey and data collection3-7 days
Layout and detail design10-15 days
Manufacture and factory trial30-45 days
Sea freight and customs15-40 days
Rail levelling by site, installation7-14 days
Commissioning, emission test, training3-5 days

Before and After

Design values from the project specification; the "before" column describes the open-floor condition found at survey, for which no measurements existed.

ItemBeforeAfter
Enclosure of the painting areaopen bay or shed, no enclosuretelescopic booth, 20 x 10 x 4 m
Floor available when not paintingpainting area blocked or sharedbooth retracted, about 85% of footprint freed
Cross-draft over the worknot controlled0.3 m/s or more (design)
Paint mist capturenone98% or more (design)
VOC treatment efficiencynone85-90% (carbon) with UV pre-oxidation (design)
Lighting at the work surfaceworkshop lighting300 lux or more, explosion-proof (design)
Noise inside the boothnot controlled80 dB(A) or less (design)

Results

  • Girders painted on stands under the gantry without a building
  • Painting continued in weather that had stopped open-air work
  • Emission test carried out at the stack after commissioning

Applicability

This configuration suits workshops where the crane moves the workpiece, painting is done in batches and the floor must return to assembly use between batches: structural steel, vessels and tanks, machinery frames, crane girders, trailer chassis and hull blocks. It is not the right choice for conveyorised lines painting every shift, for coatings that need forced cure inside the same enclosure, or where a water-curtain booth and water treatment already exist.

The results above apply to the configuration and conditions described. A different part mix, paint system, climate or emission limit changes the numbers, which is why every booth is sized from its own data.

After-Sales

Warranty options of 12, 36 or 60 months, remote diagnosis within 2 hours and on-site attendance within 72 hours where a local partner is available, plus filter media, carbon and catalyst supply for the life of the booth. Details are on our after-sales service page.

FAQ

Can the same booth paint different products?

Yes. Nothing in the enclosure is shaped to the part; the booth on this project handled the full range of plate girders and cross frames.

Why was dry capture chosen here?

Intermittent painting and frequent colour changes favour dry labyrinth-paper filtration: no water or oil circuit, and the filter wall is the only overspray-contact surface.

What did the client have to prepare?

Levelled rails to our drawing, a concrete pad for the fan and treatment unit, three-phase power to the cabinet and a crane for installation.

How was performance checked?

Travel and limit switches in both directions, drive interlock, cross-draft velocity, lighting level, noise, and stack sampling against the local limit.

Can this booth be extended later?

Frames are added in 1 m modules and the rails extended; the fan and filter wall are sized for the final length at the outset.

Get a Similar Solution

Send us the following and we return a booth layout with fan, filter and treatment sizing within a few working days:

  • Largest workpiece length, width, height and weight, and how it is handled
  • Daily paint and thinner consumption and the paint system
  • Indoor or outdoor installation, crane hook height and available floor
  • Local emission limit and workplace exposure rule

WhatsApp us about this case Contact form

Related

Provided by Lin Cong, Technical Director, MUSI Technology
Published 2026-10-01 · Updated 2026-10-01 · Last technical review: 2026-10-01