Long telescopic spray booth with blue flame-retardant PVC fabric and orange folding frames in a heavy fabrication hall with overhead cranes
CASE STUDY · 2024

Case Study: Two Telescopic Spray Booths Sharing One RCO at an Attachment Plant, Thailand

  • ClientConstruction machinery attachment manufacturer (name withheld)
  • IndustryConstruction Machinery
  • Year2024
  • LocationThailand
  • Scale12 x 5 x 4.1 m dry-filter telescopic booth (two booths on one RCO)
Southeast AsiaConstruction MachineryShared RCOThailand
Request Similar Solution Back to Cases

Summary

ObjectExcavator buckets, booms and quick couplers for a Construction machinery attachment manufacturer in Thailand
Equipment12 x 5 x 4.1 m dry-filter telescopic booth (two booths on one RCO)
Operating conditionscrane-handled batch painting, two dry filter cabinets 5, cross-draft 0.3 m/s or more
ResultBoth bays enclosed with one treatment unit and one stack
Sourceproject specification and commissioning scope; client name withheld at the client's request

Project Background

A Thai manufacturer of excavator attachments ran two painting areas 30 m apart: a large bay for booms and a smaller bay for buckets and couplers. Both needed enclosure and the plant wanted a single exhaust treatment unit rather than two.

Pain Points Before the Project

  • Two separate painting areas, each too small to justify its own RCO
  • Booms handled only by crane
  • Frequent colour changes between customer liveries
  • Paint mist reaching the assembly line next to the large bay

Why This Configuration Was Chosen

  • A 12 x 5 x 4.1 m telescopic booth for the boom bay and a smaller booth for the bucket bay, each with its own dry filter cabinet and built-in carbon stage
  • Both booths ducted to one shared RCO sized at 30,000-40,000 m3/h, with dampers set and locked at commissioning
  • Dry filtration tolerates the frequent colour changes because nothing but the filter wall touches the overspray
Inside a telescopic spray booth: dry paint-mist filter cabinet with cardboard labyrinth filters and yellow frame at the exhaust wall
Inside a telescopic spray booth: dry paint-mist filter cabinet with cardboard labyrinth filters and yellow frame at the exhaust wall

Scope of Supply

Telescopic enclosure12 x 5 x 4.1 m internal, plus a second smaller booth 30 m away; Q235 frames 50 x 70 x 2 mm, flame-retardant PVC fabric
Drive and safety2 x 3 kW explosion-proof geared motors, 8-10 m/min; interlocked drives, double limit switches, rail sweeper, jog control
Lighting100 twin-tube explosion-proof LED units, 300 lux or more
Paint mist captureTwo dry filter cabinets 5,000 x 1,000 x 2,500 mm with AP-50 glass-fibre mat and built-in carbon, 98% or more mist capture
Exhaust treatmentShared RCO, 30,000-40,000 m3/h, ducted from both booths
Fan, duct and stackRCO fan sized for both booths, 15 m stack
ControlTwo-station control cabinet, VFD on exhaust fan, emergency stop, audible-visual travel alarm
Installed powerabout 60-80 kW installed

Component brands. Key components are sourced from international first-tier brands at the client's choice; the table lists the options offered on this project.

ComponentBrand options
Exhaust fanNicotra Gebhardt, Kruger, Systemair
Geared drive motorsSEW-Eurodrive, NORD, Bonfiglioli
Explosion-proof lightingEaton Crouse-Hinds, R. STAHL, ABB
Low-voltage switchgearSchneider Electric, Siemens, ABB
Variable frequency driveABB, Danfoss, Siemens
PLC (RCO control)Siemens, Mitsubishi Electric, Omron
Filter mediaAndreae Filters, Freudenberg Viledon, Camfil
Activated carbonCalgon Carbon, Jacobi Carbons, Cabot Norit
Oxidation catalystBASF, Johnson Matthey, Clariant
Flame-retardant fabricSerge Ferrari, Sioen, Mehler Texnologies
Flexible cablesLAPP, Nexans, Prysmian
Airless spray units (client side)Graco, WIWA, WAGNER

Not included: rail levelling and civil foundations, site lifting, third-party emission testing, workpiece stands unless ordered, and the drying room where forced cure is required.

Programme

Typical programme for this booth class; the dates for each project are fixed in the contract.

StageTypical duration
Site survey and data collection3-7 days
Layout and detail design10-15 days
Manufacture and factory trial30-45 days
Sea freight and customs15-40 days
Rail levelling by site, installation7-14 days
Commissioning, emission test, training3-5 days

Before and After

Design values from the project specification; the "before" column describes the open-floor condition found at survey, for which no measurements existed.

ItemBeforeAfter
Enclosure of the painting areaopen bay or shed, no enclosuretelescopic booth, 12 x 5 x 4.1 m
Floor available when not paintingpainting area blocked or sharedbooth retracted, about 85% of footprint freed
Cross-draft over the worknot controlled0.3 m/s or more (design)
Paint mist capturenone98% or more (design)
VOC treatment efficiencynone95% or more (RCO) (design)
Lighting at the work surfaceworkshop lighting300 lux or more, explosion-proof (design)
Noise inside the boothnot controlled80 dB(A) or less (design)

Results

  • Both bays enclosed with one treatment unit and one stack
  • Filter change on the boom booth set by the differential pressure gauge
  • Assembly line next to the large bay no longer received overspray

Applicability

This configuration suits workshops where the crane moves the workpiece, painting is done in batches and the floor must return to assembly use between batches: structural steel, vessels and tanks, machinery frames, crane girders, trailer chassis and hull blocks. It is not the right choice for conveyorised lines painting every shift, for coatings that need forced cure inside the same enclosure, or where a water-curtain booth and water treatment already exist.

The results above apply to the configuration and conditions described. A different part mix, paint system, climate or emission limit changes the numbers, which is why every booth is sized from its own data.

After-Sales

Warranty options of 12, 36 or 60 months, remote diagnosis within 2 hours and on-site attendance within 72 hours where a local partner is available, plus filter media, carbon and catalyst supply for the life of the booth. Details are on our after-sales service page.

FAQ

Can the same booth paint different products?

Yes. Nothing in the enclosure is shaped to the part; the booth on this project handled the full range of excavator buckets, booms and quick couplers.

Why was dry capture chosen here?

Intermittent painting and frequent colour changes favour dry labyrinth-paper filtration: no water or oil circuit, and the filter wall is the only overspray-contact surface.

What did the client have to prepare?

Levelled rails to our drawing, a concrete pad for the fan and treatment unit, three-phase power to the cabinet and a crane for installation.

How was performance checked?

Travel and limit switches in both directions, drive interlock, cross-draft velocity, lighting level, noise, and stack sampling against the local limit.

Can this booth be extended later?

Frames are added in 1 m modules and the rails extended; the fan and filter wall are sized for the final length at the outset.

Get a Similar Solution

Send us the following and we return a booth layout with fan, filter and treatment sizing within a few working days:

  • Largest workpiece length, width, height and weight, and how it is handled
  • Daily paint and thinner consumption and the paint system
  • Indoor or outdoor installation, crane hook height and available floor
  • Local emission limit and workplace exposure rule

WhatsApp us about this case Contact form

Related

Provided by Lin Cong, Technical Director, MUSI Technology
Published 2026-10-01 · Updated 2026-10-01 · Last technical review: 2026-10-01