CASE STUDY · 2024

Case Study: Oil-Film Telescopic Spray Booth for a Process Skid Fabricator, Malaysia

  • ClientOil and gas process skid fabricator (name withheld)
  • IndustryProcess Skids
  • Year2024
  • LocationMalaysia
  • Scale13 x 5 x 3 m oil-film telescopic booth
Southeast AsiaProcess SkidsOil FilmMalaysia
Request Similar Solution Back to Cases

Summary

ObjectPump and filtration skids up to 12 m long for a Oil and gas process skid fabricator in Malaysia
Equipment13 x 5 x 3 m oil-film telescopic booth
Operating conditionscrane-handled batch painting, two oil-film purifiers 1, cross-draft 0.3 m/s or more
ResultSkids painted with instruments in place, in an enclosure that inspectors could witness
Sourceproject specification and commissioning scope; client name withheld at the client's request
Delivery record800+ coating lines for 500+ clients in 36 countries (MUSI engineering team, cumulative since 2011)
ServicesDesign, manufacturing, installation, commissioning, operator training and after-sales support from one company

Project Background

A Malaysian fabricator of pump, metering and filtration skids for offshore and downstream clients painted skids to client-specified epoxy and polyurethane systems after piping and instrumentation were fitted. Skids were moved by crane and could not be tilted, so a booth that came to the skid was the only practical enclosure.

Pain Points Before the Project

  • Skids with instruments fitted cannot be moved on their side through a booth door
  • Client inspectors required painting in a controlled, lit enclosure
  • Limited floor in a leased shed
  • Solvent-borne topcoats with a strict workplace exposure rule

Why This Configuration Was Chosen

  • A 13 x 5 x 3 m telescopic booth fits the leased bay and retracts against the end wall
  • Two oil-film purifiers handle the daily overspray of high-solids epoxy without filter waste
  • Carbon adsorption after the oil-film stage met the emission limit at this paint volume; 300 lux or more of explosion-proof lighting satisfied the inspection requirement

Scope of Supply

Telescopic enclosure13 x 5 x 3 m internal; Q235 frames 50 x 70 x 2 mm, flame-retardant PVC fabric
Drive and safety2 x 1.5 kW explosion-proof geared motors, 8-10 m/min; interlocked drives, double limit switches, rail sweeper, jog control
LightingExplosion-proof LED, 300 lux or more
Paint mist captureTwo oil-film purifiers 1,800 x 1,800 x 3,450 mm, 98% or more mist capture
Exhaust treatmentActivated carbon adsorption boxes after the oil-film stage
Fan, duct and stackCentrifugal exhaust fan sized at 0.3 m/s cross-draft (about 16,000 m3/h minimum), 15 m stack
ControlTwo-station control cabinet, VFD on exhaust fan, emergency stop, audible-visual travel alarm
Installed powerabout 30-40 kW installed

Component brands. Key components are sourced from international first-tier brands at the client's choice; the table lists the options offered on this project.

ComponentBrand options
Exhaust fanNicotra Gebhardt, Kruger, Systemair
Geared drive motorsSEW-Eurodrive, NORD, Bonfiglioli
Explosion-proof lightingEaton Crouse-Hinds, R. STAHL, ABB
Low-voltage switchgearSchneider Electric, Siemens, ABB
Variable frequency driveABB, Danfoss, Siemens
PLC (RCO control)Siemens, Mitsubishi Electric, Omron
Filter mediaAndreae Filters, Freudenberg Viledon, Camfil
Activated carbonCalgon Carbon, Jacobi Carbons, Cabot Norit
Oxidation catalystBASF, Johnson Matthey, Clariant
Flame-retardant fabricSerge Ferrari, Sioen, Mehler Texnologies
Flexible cablesLAPP, Nexans, Prysmian
Airless spray units (client side)International tier-one spray gun brands

Not included: rail levelling and civil foundations, site lifting, third-party emission testing, workpiece stands unless ordered, and the drying room where forced cure is required.

Programme

Typical programme for this booth class; the dates for each project are fixed in the contract.

StageTypical duration
Site survey and data collection3-7 days
Layout and detail design10-15 days
Manufacture and factory trial30-45 days
Sea freight and customs15-40 days
Rail levelling by site, installation7-14 days
Commissioning, emission test, training3-5 days

Before and After

Design values from the project specification; the "before" column describes the open-floor condition found at survey, for which no measurements existed.

ItemBeforeAfter
Enclosure of the painting areaopen bay or shed, no enclosuretelescopic booth, 13 x 5 x 3 m
Floor available when not paintingpainting area blocked or sharedbooth retracted, about 85% of footprint freed
Cross-draft over the worknot controlled0.3 m/s or more (design)
Paint mist capturenone98% or more (design)
VOC treatment efficiencynone85-90% (carbon) (design)
Lighting at the work surfaceworkshop lighting300 lux or more, explosion-proof (design)
Noise inside the boothnot controlled80 dB(A) or less (design)

Results

  • Skids painted with instruments in place, in an enclosure that inspectors could witness
  • Floor returned to assembly between paint jobs
  • Cross-draft of 0.3 m/s or more verified at commissioning

Applicability

This configuration suits workshops where the crane moves the workpiece, painting is done in batches and the floor must return to assembly use between batches: structural steel, vessels and tanks, machinery frames, crane girders, trailer chassis and hull blocks. It is not the right choice for conveyorised lines painting every shift, for coatings that need forced cure inside the same enclosure, or where a water-curtain booth and water treatment already exist.

The results above apply to the configuration and conditions described. A different part mix, paint system, climate or emission limit changes the numbers, which is why every booth is sized from its own data.

After-Sales

Warranty options of 12, 36 or 60 months, remote diagnosis within 2 hours and on-site attendance within 72 hours where a local partner is available, plus filter media, carbon and catalyst supply for the life of the booth. Details are on our after-sales service page.

FAQ

Can the same booth paint different products?

Yes. Nothing in the enclosure is shaped to the part; the booth on this project handled the full range of pump and filtration skids.

Why was oil-film capture chosen here?

Daily painting and a downstream treatment unit favour oil-film purifiers: oil is changed rather than filters replaced, and the catalyst is protected.

What did the client have to prepare?

Levelled rails to our drawing, a concrete pad for the fan and treatment unit, three-phase power to the cabinet and a crane for installation.

How was performance checked?

Travel and limit switches in both directions, drive interlock, cross-draft velocity, lighting level, noise, and stack sampling against the local limit.

Can this booth be extended later?

Frames are added in 1 m modules and the rails extended; the fan and filter wall are sized for the final length at the outset.

Get a Similar Solution

Send us the following and we return a booth layout with fan, filter and treatment sizing within a few working days:

  • Largest workpiece length, width, height and weight, and how it is handled
  • Daily paint and thinner consumption and the paint system
  • Indoor or outdoor installation, crane hook height and available floor
  • Local emission limit and workplace exposure rule

WhatsApp us about this case Contact form

Related

Provided by Lin Cong, Technical Director, MUSI Technology
Published 2026-10-01 · Updated 2026-10-01 · Last technical review: 2026-10-01

Q

Questions buyers ask before ordering

quotation · price · lead time · installation · warranty

What information do you need to prepare a quotation?

Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.

How much does this equipment cost?

Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our complete coating line cost guide; a configured quotation is prepared from your part data. Published indicative ex-works ranges: a complete powder coating line is roughly USD 75,000–230,000 semi-automatic, USD 200,000–600,000 for a standard automatic line and USD 600,000–2,000,000 for a high-throughput automated plant.

What is the lead time?

Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.

Do you install and train operators overseas?

Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.

What warranty and after-sales support are included?

12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.

Can the environmental equipment be supplied with the line?