Telescopic mobile spray booth fully extended over long steel beams inside a fabrication workshop, with lighting rows and white fabric walls
CASE STUDY · 2025

Case Study: Telescopic Spray Booth for a Structural Steel Fabricator, Vietnam

  • ClientStructural steel fabricator (name withheld)
  • IndustryStructural Steel
  • Year2025
  • LocationVietnam
  • Scale20 x 10 x 4 m dry-filter telescopic booth
Southeast AsiaStructural SteelTelescopic BoothVietnam
Request Similar Solution Back to Cases

Summary

ObjectH-beams, box columns and trusses up to 18 m for a Structural steel fabricator in Vietnam
Equipment20 x 10 x 4 m dry-filter telescopic booth
Operating conditionscrane-handled batch painting, dry filter wall: labyrinth paper filters plus glass-fibre bags, cross-draft 0.3 m/s or more
ResultPainting moved from the open bay into an enclosed, ventilated booth with a 0.3 m/s or more cross-draft
Sourceproject specification and commissioning scope; client name withheld at the client's request

Project Background

A structural steel fabricator in Vietnam building factory frames and warehouse portals needed to prime and topcoat members up to 18 m long in a bay that also served as the fit-up floor. Painting had been done in the open bay with mobile extraction, which left overspray on adjacent work and could not meet the plant's new emission and workplace exposure requirements.

Pain Points Before the Project

  • Members too long for the existing 8 m fixed booth door
  • Fit-up floor lost whenever a fixed booth was proposed
  • Overspray settling on welded assemblies waiting for inspection
  • No measured control of solvent exposure for painters

Why This Configuration Was Chosen

  • A 20 x 10 x 4 m telescopic booth covers a batch of four or five 18 m members on stands and retracts to about 3 m, so the fit-up floor is free between paint days
  • Dry labyrinth-paper filtration suits the zinc-rich primer and high-build epoxy overspray without a water circuit
  • Carbon boxes with UV pre-oxidation met the emission limit at the plant's intermittent painting schedule; RCO was quoted as an upgrade path
Telescopic spray booth on ground rails outside a workshop under a gantry crane, with steel structures laid out for painting
Telescopic spray booth on ground rails outside a workshop under a gantry crane, with steel structures laid out for painting

Scope of Supply

Telescopic enclosure20 x 10 x 4 m internal (retracted about 3 x 10.7 m); Q235 frames 50 x 70 x 2 mm, flame-retardant PVC fabric
Drive and safety2 x 1.5 kW explosion-proof geared motors, 8-10 m/min; interlocked drives, double limit switches, rail sweeper, jog control
Lighting60 explosion-proof LED units, 18 W each, 300 lux or more
Paint mist captureDry filter wall: labyrinth paper filters plus glass-fibre bags, 98% or more mist capture
Exhaust treatmentActivated carbon boxes plus UV photo-oxidation unit, 50,000 m3/h class
Fan, duct and stack75 kW centrifugal fan, 54,000-79,400 m3/h, 15 m stack
ControlTwo-station control cabinet, VFD on exhaust fan, emergency stop, audible-visual travel alarm
Installed powerabout 109 kW installed

Component brands. Key components are sourced from international first-tier brands at the client's choice; the table lists the options offered on this project.

ComponentBrand options
Exhaust fanNicotra Gebhardt, Kruger, Systemair
Geared drive motorsSEW-Eurodrive, NORD, Bonfiglioli
Explosion-proof lightingEaton Crouse-Hinds, R. STAHL, ABB
Low-voltage switchgearSchneider Electric, Siemens, ABB
Variable frequency driveABB, Danfoss, Siemens
PLC (RCO control)Siemens, Mitsubishi Electric, Omron
Filter mediaAndreae Filters, Freudenberg Viledon, Camfil
Activated carbonCalgon Carbon, Jacobi Carbons, Cabot Norit
Oxidation catalystBASF, Johnson Matthey, Clariant
Flame-retardant fabricSerge Ferrari, Sioen, Mehler Texnologies
Flexible cablesLAPP, Nexans, Prysmian
Airless spray units (client side)Graco, WIWA, WAGNER

Not included: rail levelling and civil foundations, site lifting, third-party emission testing, workpiece stands unless ordered, and the drying room where forced cure is required.

Programme

Typical programme for this booth class; the dates for each project are fixed in the contract.

StageTypical duration
Site survey and data collection3-7 days
Layout and detail design10-15 days
Manufacture and factory trial30-45 days
Sea freight and customs15-40 days
Rail levelling by site, installation7-14 days
Commissioning, emission test, training3-5 days

Before and After

Design values from the project specification; the "before" column describes the open-floor condition found at survey, for which no measurements existed.

ItemBeforeAfter
Enclosure of the painting areaopen bay or shed, no enclosuretelescopic booth, 20 x 10 x 4 m
Floor available when not paintingpainting area blocked or sharedbooth retracted, about 85% of footprint freed
Cross-draft over the worknot controlled0.3 m/s or more (design)
Paint mist capturenone98% or more (design)
VOC treatment efficiencynone85-90% (carbon) with UV pre-oxidation (design)
Lighting at the work surfaceworkshop lighting300 lux or more, explosion-proof (design)
Noise inside the boothnot controlled80 dB(A) or less (design)

Results

  • Painting moved from the open bay into an enclosed, ventilated booth with a 0.3 m/s or more cross-draft
  • Fit-up work continued on the same floor between paint batches
  • Emission test at commissioning was carried out against the local limit

Applicability

This configuration suits workshops where the crane moves the workpiece, painting is done in batches and the floor must return to assembly use between batches: structural steel, vessels and tanks, machinery frames, crane girders, trailer chassis and hull blocks. It is not the right choice for conveyorised lines painting every shift, for coatings that need forced cure inside the same enclosure, or where a water-curtain booth and water treatment already exist.

The results above apply to the configuration and conditions described. A different part mix, paint system, climate or emission limit changes the numbers, which is why every booth is sized from its own data.

After-Sales

Warranty options of 12, 36 or 60 months, remote diagnosis within 2 hours and on-site attendance within 72 hours where a local partner is available, plus filter media, carbon and catalyst supply for the life of the booth. Details are on our after-sales service page.

FAQ

Can the same booth paint different products?

Yes. Nothing in the enclosure is shaped to the part; the booth on this project handled the full range of h-beams, box columns and trusses.

Why was dry capture chosen here?

Intermittent painting and frequent colour changes favour dry labyrinth-paper filtration: no water or oil circuit, and the filter wall is the only overspray-contact surface.

What did the client have to prepare?

Levelled rails to our drawing, a concrete pad for the fan and treatment unit, three-phase power to the cabinet and a crane for installation.

How was performance checked?

Travel and limit switches in both directions, drive interlock, cross-draft velocity, lighting level, noise, and stack sampling against the local limit.

Can this booth be extended later?

Frames are added in 1 m modules and the rails extended; the fan and filter wall are sized for the final length at the outset.

Get a Similar Solution

Send us the following and we return a booth layout with fan, filter and treatment sizing within a few working days:

  • Largest workpiece length, width, height and weight, and how it is handled
  • Daily paint and thinner consumption and the paint system
  • Indoor or outdoor installation, crane hook height and available floor
  • Local emission limit and workplace exposure rule

WhatsApp us about this case Contact form

Related

Provided by Lin Cong, Technical Director, MUSI Technology
Published 2026-10-01 · Updated 2026-10-01 · Last technical review: 2026-10-01