Telescopic spray booth with orange folding frames retracted beside a pressure vessel workshop, exhaust duct on the roof
CASE STUDY · 2023

Case Study: Oil-Film Telescopic Spray Booth with RCO for a Mining Equipment Rebuild Shop, Kazakhstan

  • ClientMining equipment repair and rebuild workshop (name withheld)
  • IndustryMining Equipment
  • Year2023
  • LocationKazakhstan
  • Scale12 x 7 x 4.5 m oil-film telescopic booth with RCO
Central AsiaMining EquipmentRCOKazakhstan
Request Similar Solution Back to Cases

Summary

ObjectDump truck bodies, mill shells and loader frames for a Mining equipment repair and rebuild workshop in Kazakhstan
Equipment12 x 7 x 4.5 m oil-film telescopic booth with RCO
Operating conditionscrane-handled batch painting, three oil-film purifiers 1, cross-draft 0.3 m/s or more
ResultRepainting kept indoors through the winter inside a ventilated enclosure
Sourceproject specification and commissioning scope; client name withheld at the client's request

Project Background

A rebuild workshop in Kazakhstan refurbished dump truck bodies, mill shells and loader frames for regional mines and repainted them after repair. Parts were heavy, irregular and handled only by crane, and the workshop's winter climate meant painting had to stay indoors.

Pain Points Before the Project

  • Irregular parts up to 10 t moved by crane only
  • Daily painting through the winter with solvent-borne systems
  • Emission limit at the new site required more than carbon boxes
  • Cold-climate building could not be opened for ventilation

Why This Configuration Was Chosen

  • A 12 x 7 x 4.5 m telescopic booth in the rebuild bay, closing around parts on stands
  • Three oil-film purifiers for daily overspray with oil changes instead of filter waste
  • RCO at 30,000 m3/h with a 60 kW start-up heater and heat recovery for the desorption cycle
Inside a telescopic spray booth: dry paint-mist filter cabinet with cardboard labyrinth filters and yellow frame at the exhaust wall
Inside a telescopic spray booth: dry paint-mist filter cabinet with cardboard labyrinth filters and yellow frame at the exhaust wall

Scope of Supply

Telescopic enclosure12 x 7 x 4.5 m internal; Q235 frames 50 x 70 x 2 mm, flame-retardant PVC fabric
Drive and safety2 x 1.5 kW explosion-proof geared motors, 8-10 m/min; interlocked drives, double limit switches, rail sweeper, jog control
LightingExplosion-proof LED, 300 lux or more
Paint mist captureThree oil-film purifiers 1,800 x 1,800 x 3,450 mm, 98% or more mist capture
Exhaust treatmentAdsorption-desorption unit with catalytic oxidation (RCO), 30,000 m3/h, three honeycomb carbon beds
Fan, duct and stack45 kW adsorption fan, 60 kW start-up heater, 3 kW desorption fan, 15 m stack
ControlTwo-station control cabinet, VFD on exhaust fan, emergency stop, audible-visual travel alarm
Installed powerabout 110 kW installed (heater on start-up only)

Component brands. Key components are sourced from international first-tier brands at the client's choice; the table lists the options offered on this project.

ComponentBrand options
Exhaust fanNicotra Gebhardt, Kruger, Systemair
Geared drive motorsSEW-Eurodrive, NORD, Bonfiglioli
Explosion-proof lightingEaton Crouse-Hinds, R. STAHL, ABB
Low-voltage switchgearSchneider Electric, Siemens, ABB
Variable frequency driveABB, Danfoss, Siemens
PLC (RCO control)Siemens, Mitsubishi Electric, Omron
Filter mediaAndreae Filters, Freudenberg Viledon, Camfil
Activated carbonCalgon Carbon, Jacobi Carbons, Cabot Norit
Oxidation catalystBASF, Johnson Matthey, Clariant
Flame-retardant fabricSerge Ferrari, Sioen, Mehler Texnologies
Flexible cablesLAPP, Nexans, Prysmian
Airless spray units (client side)Graco, WIWA, WAGNER

Not included: rail levelling and civil foundations, site lifting, third-party emission testing, workpiece stands unless ordered, and the drying room where forced cure is required.

Programme

Typical programme for this booth class; the dates for each project are fixed in the contract.

StageTypical duration
Site survey and data collection3-7 days
Layout and detail design10-15 days
Manufacture and factory trial30-45 days
Sea freight and customs15-40 days
Rail levelling by site, installation7-14 days
Commissioning, emission test, training3-5 days

Before and After

Design values from the project specification; the "before" column describes the open-floor condition found at survey, for which no measurements existed.

ItemBeforeAfter
Enclosure of the painting areaopen bay or shed, no enclosuretelescopic booth, 12 x 7 x 4.5 m
Floor available when not paintingpainting area blocked or sharedbooth retracted, about 85% of footprint freed
Cross-draft over the worknot controlled0.3 m/s or more (design)
Paint mist capturenone98% or more (design)
VOC treatment efficiencynone95% or more (RCO) (design)
Lighting at the work surfaceworkshop lighting300 lux or more, explosion-proof (design)
Noise inside the boothnot controlled80 dB(A) or less (design)

Results

  • Repainting kept indoors through the winter inside a ventilated enclosure
  • RCO commissioned with automatic bed switching
  • Booth retracted to free the bay for mechanical work between paint jobs

Applicability

This configuration suits workshops where the crane moves the workpiece, painting is done in batches and the floor must return to assembly use between batches: structural steel, vessels and tanks, machinery frames, crane girders, trailer chassis and hull blocks. It is not the right choice for conveyorised lines painting every shift, for coatings that need forced cure inside the same enclosure, or where a water-curtain booth and water treatment already exist.

The results above apply to the configuration and conditions described. A different part mix, paint system, climate or emission limit changes the numbers, which is why every booth is sized from its own data.

After-Sales

Warranty options of 12, 36 or 60 months, remote diagnosis within 2 hours and on-site attendance within 72 hours where a local partner is available, plus filter media, carbon and catalyst supply for the life of the booth. Details are on our after-sales service page.

FAQ

Can the same booth paint different products?

Yes. Nothing in the enclosure is shaped to the part; the booth on this project handled the full range of dump truck bodies, mill shells and loader frames.

Why was oil-film capture chosen here?

Daily painting and a downstream treatment unit favour oil-film purifiers: oil is changed rather than filters replaced, and the catalyst is protected.

What did the client have to prepare?

Levelled rails to our drawing, a concrete pad for the fan and treatment unit, three-phase power to the cabinet and a crane for installation.

How was performance checked?

Travel and limit switches in both directions, drive interlock, cross-draft velocity, lighting level, noise, and stack sampling against the local limit.

Can this booth be extended later?

Frames are added in 1 m modules and the rails extended; the fan and filter wall are sized for the final length at the outset.

Get a Similar Solution

Send us the following and we return a booth layout with fan, filter and treatment sizing within a few working days:

  • Largest workpiece length, width, height and weight, and how it is handled
  • Daily paint and thinner consumption and the paint system
  • Indoor or outdoor installation, crane hook height and available floor
  • Local emission limit and workplace exposure rule

WhatsApp us about this case Contact form

Related

Provided by Lin Cong, Technical Director, MUSI Technology
Published 2026-10-01 · Updated 2026-10-01 · Last technical review: 2026-10-01