Spray painting line with booth and conveyor
CASE STUDY · 2026

Case Study: Vehicle Body Painting Line, Mexico

  • ClientAssembly plant of a Chinese automaker
  • IndustryAutomotive Parts
  • Year2026
  • LocationMexico
  • ScaleVehicle bodies for SUVs, pickups and light commercial vehicles
Vehicle AssemblyBody PaintingMexico
Request Similar Solution Back to Cases

Summary

A vehicle body painting line for the Mexican assembly plant of a major Chinese automaker in the state of Hidalgo, which started production in 2017 with SUVs and by 2025 was assembling more than twenty models including pickups, light trucks, vans and an electric car. The line is built around controlled booth air, with filtered supply and exhaust keeping the booths clean and balanced, viewing windows for operators, and a body conveyor carrying each body through pretreatment, painting, drying and cooling in a fixed sequence. The line serves vehicle production at the plant in 2026.

Project Background

The client is the Mexican assembly plant of a major Chinese automaker, in the state of Hidalgo. It started production in 2017 with SUVs and by 2025 was assembling more than twenty models, from SUVs and pickups to light trucks, vans and an electric car, with an expansion under way to double its capacity. MUSI supplied a body painting line for the plant.

The plant assembles and distributes vehicles for the JAC brand in Mexico, currently the J4, SEI2 and SEI3 models with further models in preparation, and has announced an investment to double its capacity.

The Challenge

Vehicle bodies are the most visible painted surface a car plant produces. Every panel has to come out with the same colour, gloss and film build, dust must be kept off the wet paint, and the paint shop has to keep pace with an assembly plant that is adding models and lines.

MUSI's Solution

MUSI supplied a body painting line built around controlled booth air: filtered supply air and exhaust keep the booths clean and balanced, viewing windows let operators watch the spraying, and the conveyor carries each body through pretreatment, painting, drying and cooling in a fixed sequence.

Paint booth with viewing windows and air supply ducts
Paint booth with viewing windows and air supply ducts

Equipment Scope

  • Pretreatment for vehicle bodies
  • Paint booths with filtered air supply and exhaust
  • Drying ovens and cooling
  • Body conveyor
  • Exhaust and VOC treatment

Results

The line serves vehicle production at the plant, painting bodies for the models assembled there.

Selection logic: why this configuration

Booth air balance was made the design centre because on a body line dust in the film and colour drift between panels are the reject causes, and both come from unbalanced or unfiltered booth air. A fixed-sequence body conveyor was specified rather than transfer carts because an assembly plant adding models needs a steady takt, and viewing windows were included so operators check spraying without entering the booth.

Scope of supply and key components

ItemSpecificationNotes
PretreatmentFor vehicle bodies
Paint boothsFiltered air supply and exhaust, viewing windows
Drying ovensWith cooling
Body conveyorFixed sequence through pretreatment, paint, dry, cool
Exhaust and VOC treatment

Key components

Key components are available from international brands, configurable per customer specification, so that spare parts can be sourced locally over the life of the line. Brand names below are the usual options for this type of equipment; the brands actually fitted are fixed in the contract specification.

ComponentBrands available on request
Automatic liquid guns, pumps and 2K proportionersInternational tier-one spray gun, pump and 2K proportioner brands
Painting robotsABB IRB 5500, FANUC P-350iA, Yaskawa MOTOMAN MPX series, KUKA, Kawasaki
Booth ceiling and intake filter mediaFreudenberg Viledon, AAF SureStop, Camfil, MANN+HUMMEL
Oven and dryer gas burnersRiello RS series, Weishaupt monarch WM-G, Baltur TBG, Honeywell Maxon OVENPAK, Eclipse
PLC and HMISiemens SIMATIC S7-1500, Mitsubishi Electric MELSEC iQ-R, Schneider Electric Modicon, OMRON NX, Rockwell Automation Allen-Bradley
Variable-frequency drivesABB ACS580, Siemens SINAMICS G120, Danfoss VLT, Schneider Electric Altivar, Yaskawa, Mitsubishi Electric
Pretreatment pumps and chemistryGrundfos CR, KSB Etanorm, Xylem; Henkel BONDERITE, Chemetall Gardobond, PPG Zircobond, Nippon Paint
RTO ceramic media and burnersLantec MLM, Honeywell Maxon line burners, Riello RS, Eclipse

Not included in the scope of supply

  • Civil works, foundations and pits
  • Building services up to the battery limit: power supply, gas, compressed air, water and drainage
  • Local permits, emission approvals and third-party inspections
  • Paint or powder supply, unless stated in the contract

Services included with every line: engineering design, manufacturing, shipping documentation, installation supervision, commissioning, operator training, warranty and spare parts.

Typical programme

The durations below are typical for equipment of this class and are given for planning; they are not the recorded schedule of this project. A complete line usually runs 90–180 days from contract to acceptance, a single unit 30–60 days.

StageTypical durationWhat happens
Site survey and workpiece review5–10 daysRemote review of drawings and photos, or an engineer visit
Layout and detail design15–30 daysLayout drawing, utilities list and specification sign-off
Manufacturing45–90 daysBooths, ovens, conveyor, pretreatment and controls built and pre-assembled at the works
Shipping20–45 daysSea freight; equipment shipped in sections for on-site assembly
Installation15–40 daysMUSI supervision with the client's installation crew or MUSI crew
Commissioning, training and acceptance7–15 daysTrial runs on the client's parts, operator training, acceptance record

Applicability and limits

The line is sized to the body dimensions and takt of this plant; a plant with a different model mix or a higher line rate needs its own booth count and oven length. The paint system and colour range are set by the automaker and are not part of the equipment scope.

Results shown in this case study reflect the stated operating conditions and should not be interpreted as guaranteed performance under different feed, production, environmental, or site conditions.

After-sales and spare parts

Warranty on a MUSI coating line runs from acceptance: 12 months on the complete line excluding consumables, 36 months on critical components such as motors, drives and the PLC, and 60 months on structural parts such as steel structure, ducting and oven bodies. Failures within warranty, excluding misuse, are repaired free of charge.

Support starts remotely: the service line is staffed around the clock, a preliminary diagnosis with recommendations is given within 2 hours, and where a site visit is needed an engineer reaches any major city within 72 hours. A spare-parts inventory is held at the Changzhou headquarters with same-day shipping, and customers can keep a dedicated parts stock at MUSI for emergencies. Details are on the after-sales service page.

Who installed this line?

This line was installed and commissioned on site by MUSI engineers. Other lines MUSI engineers have installed on site are listed on the installation and commissioning page.

FAQ

What matters most on a vehicle body paint booth? Air: filtered supply, balanced exhaust and a steady downdraft, so dust stays out of the wet film and every panel receives the same conditions.

Why viewing windows on the booths? So operators and quality staff watch spraying in real time without entering the booth and disturbing the air.

How does the body move through the line? On a body conveyor in a fixed sequence: pretreatment, painting, drying and cooling, so every body follows the same route at the plant takt.

Which vehicles does the plant build? JAC-brand models assembled and distributed in Mexico, including the J4, SEI2 and SEI3, with more models planned as capacity doubles.

Does the scope include the paint? No; the automaker specifies the paint system and colours. MUSI supplied the booths, ovens, conveyor and air handling.

Next step: a configuration proposal for a similar line

If your parts, volumes or plant conditions are close to this project, MUSI can return a line configuration and layout proposal. To prepare it we need four things:

  • Photos and dimensions of the workpieces, with weight and material
  • Required output (pieces per hour or per day, and shifts)
  • Number of colours and how often colour changes are needed
  • Available floor space and ceiling height, with the utilities on site

Message us on WhatsApp with these details, or use the quotation form.

Published 2026-09-26 · Updated 2026-09-30 · Last technical review: 2026-09-30

Q

Questions buyers ask before ordering

quotation · price · lead time · installation · warranty

What information do you need to prepare a quotation?

Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.

How much does this equipment cost?

Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our complete coating line cost guide; a configured quotation is prepared from your part data. Published indicative ex-works ranges: a complete powder coating line is roughly USD 75,000–230,000 semi-automatic, USD 200,000–600,000 for a standard automatic line and USD 600,000–2,000,000 for a high-throughput automated plant.

What is the lead time?

Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.

Do you install and train operators overseas?

Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.

What warranty and after-sales support are included?

12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.

Can the environmental equipment be supplied with the line?

Yes. VOC treatment (RTO, RCO, activated carbon, zeolite rotor), dust collection and paint wastewater treatment are supplied with the coating line under one contract; MUSI has equipped 50+ coating facilities whose projects all passed local environmental compliance reviews.

Request a configured quotationWhatsApp +86 181 5173 1332 · lin@coating-spray.com

Get a Similar Solution

If your industry and requirements match this case, contact MUSI to schedule a free consultation. We'll design an optimal solution based on your specific workpieces, capacity, and facility.

Provided by Lin Cong, Technical Director, MUSI Technology