Front view of a telescopic spray booth showing the dry paint-mist filter cabinet, folded fabric roof and orange folding frames
CASE STUDY · 2024

Case Study: Oil-Film Telescopic Spray Booth for a Tank and Pipe Spool Fabricator, Saudi Arabia

  • ClientStorage tank and pipe spool fabricator (name withheld)
  • IndustryStorage Tanks
  • Year2024
  • LocationSaudi Arabia
  • Scale13 x 5 x 3 m oil-film telescopic booth
Middle EastStorage TanksPipe SpoolsSaudi Arabia
Request Similar Solution Back to Cases

Summary

ObjectTank shell sections and pipe spools for a Storage tank and pipe spool fabricator in Saudi Arabia
Equipment13 x 5 x 3 m oil-film telescopic booth
Operating conditionscrane-handled batch painting, two oil-film purifiers 1, cross-draft 0.3 m/s or more
ResultDust-free enclosure for inspection-witnessed painting
Sourceproject specification and commissioning scope; client name withheld at the client's request

Project Background

A fabricator in Saudi Arabia producing storage tank shell sections and pipe spools for petrochemical projects painted to client specifications with epoxy and polyurethane systems. Parts were batch-painted after fit-up and the plant needed an enclosure that tolerated high ambient temperature and dust.

Pain Points Before the Project

  • Dust from the surrounding site settling on wet paint
  • Batch painting with heavy overspray on curved shell sections
  • High ambient temperature limiting fabric choice
  • Painting had to be witnessed by client inspectors

Why This Configuration Was Chosen

  • A 13 x 5 x 3 m telescopic booth with UV-stabilised flame-retardant fabric and explosion-proof lighting to 300 lux or more
  • Two oil-film purifiers for the batch overspray, followed by carbon adsorption boxes
  • Fixed end and stack placed on the shaded side of the bay to limit heat on the treatment unit
Inside a telescopic spray booth: dry paint-mist filter cabinet with cardboard labyrinth filters and yellow frame at the exhaust wall
Inside a telescopic spray booth: dry paint-mist filter cabinet with cardboard labyrinth filters and yellow frame at the exhaust wall

Scope of Supply

Telescopic enclosure13 x 5 x 3 m internal; Q235 frames 50 x 70 x 2 mm, flame-retardant PVC fabric
Drive and safety2 x 1.5 kW explosion-proof geared motors, 8-10 m/min; interlocked drives, double limit switches, rail sweeper, jog control
LightingExplosion-proof LED, 300 lux or more
Paint mist captureTwo oil-film purifiers 1,800 x 1,800 x 3,450 mm, 98% or more mist capture
Exhaust treatmentActivated carbon adsorption boxes after the oil-film stage
Fan, duct and stackCentrifugal exhaust fan sized at 0.3 m/s cross-draft (about 16,000 m3/h minimum), 15 m stack
ControlTwo-station control cabinet, VFD on exhaust fan, emergency stop, audible-visual travel alarm
Installed powerabout 30-40 kW installed

Component brands. Key components are sourced from international first-tier brands at the client's choice; the table lists the options offered on this project.

ComponentBrand options
Exhaust fanNicotra Gebhardt, Kruger, Systemair
Geared drive motorsSEW-Eurodrive, NORD, Bonfiglioli
Explosion-proof lightingEaton Crouse-Hinds, R. STAHL, ABB
Low-voltage switchgearSchneider Electric, Siemens, ABB
Variable frequency driveABB, Danfoss, Siemens
PLC (RCO control)Siemens, Mitsubishi Electric, Omron
Filter mediaAndreae Filters, Freudenberg Viledon, Camfil
Activated carbonCalgon Carbon, Jacobi Carbons, Cabot Norit
Oxidation catalystBASF, Johnson Matthey, Clariant
Flame-retardant fabricSerge Ferrari, Sioen, Mehler Texnologies
Flexible cablesLAPP, Nexans, Prysmian
Airless spray units (client side)Graco, WIWA, WAGNER

Not included: rail levelling and civil foundations, site lifting, third-party emission testing, workpiece stands unless ordered, and the drying room where forced cure is required.

Programme

Typical programme for this booth class; the dates for each project are fixed in the contract.

StageTypical duration
Site survey and data collection3-7 days
Layout and detail design10-15 days
Manufacture and factory trial30-45 days
Sea freight and customs15-40 days
Rail levelling by site, installation7-14 days
Commissioning, emission test, training3-5 days

Before and After

Design values from the project specification; the "before" column describes the open-floor condition found at survey, for which no measurements existed.

ItemBeforeAfter
Enclosure of the painting areaopen bay or shed, no enclosuretelescopic booth, 13 x 5 x 3 m
Floor available when not paintingpainting area blocked or sharedbooth retracted, about 85% of footprint freed
Cross-draft over the worknot controlled0.3 m/s or more (design)
Paint mist capturenone98% or more (design)
VOC treatment efficiencynone85-90% (carbon) (design)
Lighting at the work surfaceworkshop lighting300 lux or more, explosion-proof (design)
Noise inside the boothnot controlled80 dB(A) or less (design)

Results

  • Dust-free enclosure for inspection-witnessed painting
  • Oil-film stage handling batch overspray with scheduled oil changes
  • Booth retracted between batches to free the fit-up area

Applicability

This configuration suits workshops where the crane moves the workpiece, painting is done in batches and the floor must return to assembly use between batches: structural steel, vessels and tanks, machinery frames, crane girders, trailer chassis and hull blocks. It is not the right choice for conveyorised lines painting every shift, for coatings that need forced cure inside the same enclosure, or where a water-curtain booth and water treatment already exist.

The results above apply to the configuration and conditions described. A different part mix, paint system, climate or emission limit changes the numbers, which is why every booth is sized from its own data.

After-Sales

Warranty options of 12, 36 or 60 months, remote diagnosis within 2 hours and on-site attendance within 72 hours where a local partner is available, plus filter media, carbon and catalyst supply for the life of the booth. Details are on our after-sales service page.

FAQ

Can the same booth paint different products?

Yes. Nothing in the enclosure is shaped to the part; the booth on this project handled the full range of tank shell sections and pipe spools.

Why was oil-film capture chosen here?

Daily painting and a downstream treatment unit favour oil-film purifiers: oil is changed rather than filters replaced, and the catalyst is protected.

What did the client have to prepare?

Levelled rails to our drawing, a concrete pad for the fan and treatment unit, three-phase power to the cabinet and a crane for installation.

How was performance checked?

Travel and limit switches in both directions, drive interlock, cross-draft velocity, lighting level, noise, and stack sampling against the local limit.

Can this booth be extended later?

Frames are added in 1 m modules and the rails extended; the fan and filter wall are sized for the final length at the outset.

Get a Similar Solution

Send us the following and we return a booth layout with fan, filter and treatment sizing within a few working days:

  • Largest workpiece length, width, height and weight, and how it is handled
  • Daily paint and thinner consumption and the paint system
  • Indoor or outdoor installation, crane hook height and available floor
  • Local emission limit and workplace exposure rule