Case Study: Oil-Film Telescopic Spray Booth for a Tank and Pipe Spool Fabricator, Saudi Arabia
Summary
| Object | Tank shell sections and pipe spools for a Storage tank and pipe spool fabricator in Saudi Arabia |
|---|---|
| Equipment | 13 x 5 x 3 m oil-film telescopic booth |
| Operating conditions | crane-handled batch painting, two oil-film purifiers 1, cross-draft 0.3 m/s or more |
| Result | Dust-free enclosure for inspection-witnessed painting |
| Source | project specification and commissioning scope; client name withheld at the client's request |
Project Background
A fabricator in Saudi Arabia producing storage tank shell sections and pipe spools for petrochemical projects painted to client specifications with epoxy and polyurethane systems. Parts were batch-painted after fit-up and the plant needed an enclosure that tolerated high ambient temperature and dust.
Pain Points Before the Project
- Dust from the surrounding site settling on wet paint
- Batch painting with heavy overspray on curved shell sections
- High ambient temperature limiting fabric choice
- Painting had to be witnessed by client inspectors
Why This Configuration Was Chosen
- A 13 x 5 x 3 m telescopic booth with UV-stabilised flame-retardant fabric and explosion-proof lighting to 300 lux or more
- Two oil-film purifiers for the batch overspray, followed by carbon adsorption boxes
- Fixed end and stack placed on the shaded side of the bay to limit heat on the treatment unit

Scope of Supply
| Telescopic enclosure | 13 x 5 x 3 m internal; Q235 frames 50 x 70 x 2 mm, flame-retardant PVC fabric |
|---|---|
| Drive and safety | 2 x 1.5 kW explosion-proof geared motors, 8-10 m/min; interlocked drives, double limit switches, rail sweeper, jog control |
| Lighting | Explosion-proof LED, 300 lux or more |
| Paint mist capture | Two oil-film purifiers 1,800 x 1,800 x 3,450 mm, 98% or more mist capture |
| Exhaust treatment | Activated carbon adsorption boxes after the oil-film stage |
| Fan, duct and stack | Centrifugal exhaust fan sized at 0.3 m/s cross-draft (about 16,000 m3/h minimum), 15 m stack |
| Control | Two-station control cabinet, VFD on exhaust fan, emergency stop, audible-visual travel alarm |
| Installed power | about 30-40 kW installed |
Component brands. Key components are sourced from international first-tier brands at the client's choice; the table lists the options offered on this project.
| Component | Brand options |
|---|---|
| Exhaust fan | Nicotra Gebhardt, Kruger, Systemair |
| Geared drive motors | SEW-Eurodrive, NORD, Bonfiglioli |
| Explosion-proof lighting | Eaton Crouse-Hinds, R. STAHL, ABB |
| Low-voltage switchgear | Schneider Electric, Siemens, ABB |
| Variable frequency drive | ABB, Danfoss, Siemens |
| PLC (RCO control) | Siemens, Mitsubishi Electric, Omron |
| Filter media | Andreae Filters, Freudenberg Viledon, Camfil |
| Activated carbon | Calgon Carbon, Jacobi Carbons, Cabot Norit |
| Oxidation catalyst | BASF, Johnson Matthey, Clariant |
| Flame-retardant fabric | Serge Ferrari, Sioen, Mehler Texnologies |
| Flexible cables | LAPP, Nexans, Prysmian |
| Airless spray units (client side) | Graco, WIWA, WAGNER |
Not included: rail levelling and civil foundations, site lifting, third-party emission testing, workpiece stands unless ordered, and the drying room where forced cure is required.
Programme
Typical programme for this booth class; the dates for each project are fixed in the contract.
| Stage | Typical duration |
|---|---|
| Site survey and data collection | 3-7 days |
| Layout and detail design | 10-15 days |
| Manufacture and factory trial | 30-45 days |
| Sea freight and customs | 15-40 days |
| Rail levelling by site, installation | 7-14 days |
| Commissioning, emission test, training | 3-5 days |
Before and After
Design values from the project specification; the "before" column describes the open-floor condition found at survey, for which no measurements existed.
| Item | Before | After |
|---|---|---|
| Enclosure of the painting area | open bay or shed, no enclosure | telescopic booth, 13 x 5 x 3 m |
| Floor available when not painting | painting area blocked or shared | booth retracted, about 85% of footprint freed |
| Cross-draft over the work | not controlled | 0.3 m/s or more (design) |
| Paint mist capture | none | 98% or more (design) |
| VOC treatment efficiency | none | 85-90% (carbon) (design) |
| Lighting at the work surface | workshop lighting | 300 lux or more, explosion-proof (design) |
| Noise inside the booth | not controlled | 80 dB(A) or less (design) |
Results
- Dust-free enclosure for inspection-witnessed painting
- Oil-film stage handling batch overspray with scheduled oil changes
- Booth retracted between batches to free the fit-up area
Applicability
This configuration suits workshops where the crane moves the workpiece, painting is done in batches and the floor must return to assembly use between batches: structural steel, vessels and tanks, machinery frames, crane girders, trailer chassis and hull blocks. It is not the right choice for conveyorised lines painting every shift, for coatings that need forced cure inside the same enclosure, or where a water-curtain booth and water treatment already exist.
The results above apply to the configuration and conditions described. A different part mix, paint system, climate or emission limit changes the numbers, which is why every booth is sized from its own data.
After-Sales
Warranty options of 12, 36 or 60 months, remote diagnosis within 2 hours and on-site attendance within 72 hours where a local partner is available, plus filter media, carbon and catalyst supply for the life of the booth. Details are on our after-sales service page.
FAQ
Can the same booth paint different products?
Yes. Nothing in the enclosure is shaped to the part; the booth on this project handled the full range of tank shell sections and pipe spools.
Why was oil-film capture chosen here?
Daily painting and a downstream treatment unit favour oil-film purifiers: oil is changed rather than filters replaced, and the catalyst is protected.
What did the client have to prepare?
Levelled rails to our drawing, a concrete pad for the fan and treatment unit, three-phase power to the cabinet and a crane for installation.
How was performance checked?
Travel and limit switches in both directions, drive interlock, cross-draft velocity, lighting level, noise, and stack sampling against the local limit.
Can this booth be extended later?
Frames are added in 1 m modules and the rails extended; the fan and filter wall are sized for the final length at the outset.
Get a Similar Solution
Send us the following and we return a booth layout with fan, filter and treatment sizing within a few working days:
- Largest workpiece length, width, height and weight, and how it is handled
- Daily paint and thinner consumption and the paint system
- Indoor or outdoor installation, crane hook height and available floor
- Local emission limit and workplace exposure rule
WhatsApp us about this case Contact form
Related
- Telescopic mobile spray booth (product page)
- What is a telescopic spray booth and how does it work?
- How to size a telescopic spray booth
- VOC treatment: carbon, UV or RCO
- Paint mixing room
Provided by Lin Cong, Technical Director, MUSI Technology
Published 2026-10-01 · Updated 2026-10-01 · Last technical review: 2026-10-01