Case Study: Complete Coating Workshop EPC Project
Summary
A turnkey coating workshop for a mining equipment company in Chile that consolidated four older coating areas into a new 6,000 m² workshop, delivered by MUSI as EPC contractor in six months from design to production. The scope covered pretreatment, five spray booths, five ovens, complete VOC treatment, and the civil, HVAC, fire-safety and environmental works around them, with up to 80 people on site at peak. Consolidation cut labour by 40% and energy by 28% and raised capacity by 50%, as reported after the 2023 start-up.
Project Background
The client is a large mining equipment company in Chile, deciding to consolidate coating operations from 4 old workshops into a new 6,000 m² coating workshop. MUSI won the bid for the complete coating engineering EPC project.
The Challenge
Project scope: 7 types of coating equipment, complete air/water/electric/gas auxiliary systems — coordination across civil works, HVAC, fire safety, environmental disciplines. Tight schedule (production launch within 6 months).
MUSI's Solution
MUSI as EPC contractor managed design-procurement-construction-commissioning: months 1-2 design + permits, months 3-5 equipment manufacturing + on-site construction, month 6 commissioning and launch. Established on-site project headquarters for unified management.
Equipment Configuration
| Project type | Complete coating workshop EPC |
|---|---|
| Workshop area | 6,000 m² |
| Equipment list | Pretreatment + 5 spray booths + 5 ovens + total environmental |
| Auxiliary works | Civil + HVAC + fire safety + environmental |
| Timeline | 6 months |
| Personnel | Up to 80+ on-site at peak |
| Total investment | Approximately $5 M USD |
| Delivery | EPC turnkey |
Equipment used on this line
- Automatic spray coating lines — overhead chain, floor belt and robotic flexible lines
- VOCs and environmental equipment — RTO, RCO, activated carbon, zeolite rotor and wastewater treatment
Implementation
At peak, 8 trades worked simultaneously on-site. MUSI's project office maintained daily morning briefings, weekly plans, and monthly milestones.
Results
Project delivered on schedule in 6 months with all inspections passed first-attempt. Consolidating 4 dispersed coating areas reduced labor 40%, energy 28%, and increased capacity 50%.
Client Feedback
"EPC turnkey demands exceptional management capability from suppliers. MUSI proved they're not just an equipment vendor but also a qualified engineering general contractor."
— Project Manager, Client Side
Selection logic: why this configuration
A single EPC contract was chosen over separate equipment and construction contracts because the client's six-month deadline left no time to coordinate eight trades across two contractors. Five booths and five ovens, rather than one large line, were specified because mining equipment parts range from small brackets to large structures with different coating systems and cure profiles. An on-site project office with daily briefings was set up because the disciplines overlapped on the same floor.
Scope of supply and key components
| Item | Specification | Notes |
|---|---|---|
| Coating workshop | 6,000 m², EPC turnkey | Design, permits, procurement, construction, commissioning |
| Pretreatment | Blast and chemical pretreatment stations | |
| Spray booths | 5, sized to the part families | |
| Ovens | 5 drying and curing ovens | |
| VOC treatment | Plant-wide exhaust collection and treatment | |
| Auxiliary works | Civil, HVAC, fire safety, environmental | Included in this EPC project |
Key components
Key components are available from international brands, configurable per customer specification, so that spare parts can be sourced locally over the life of the line. Brand names below are the usual options for this type of equipment; the brands actually fitted are fixed in the contract specification.
| Component | Brands available on request |
|---|---|
| Automatic liquid guns, pumps and 2K proportioners | International tier-one spray gun, pump and 2K proportioner brands |
| Automatic powder guns and powder feed | International tier-one powder spray gun brands |
| Oven and dryer gas burners | Riello RS series, Weishaupt monarch WM-G, Baltur TBG, Honeywell Maxon OVENPAK, Eclipse |
| PLC and HMI | Siemens SIMATIC S7-1500, Mitsubishi Electric MELSEC iQ-R, Schneider Electric Modicon, OMRON NX, Rockwell Automation Allen-Bradley |
| Variable-frequency drives | ABB ACS580, Siemens SINAMICS G120, Danfoss VLT, Schneider Electric Altivar, Yaskawa, Mitsubishi Electric |
| Booth ceiling and intake filter media | Freudenberg Viledon, AAF SureStop, Camfil, MANN+HUMMEL |
| RTO ceramic media and burners | Lantec MLM, Honeywell Maxon line burners, Riello RS, Eclipse |
| Sensors and temperature controllers | SICK, Pepperl+Fuchs, OMRON E5CC, Honeywell UDC, Yokogawa UT, ifm, KEYENCE |
Not included in the scope of supply
- None beyond the contract battery limits: this project was delivered turnkey
Services included with every line: engineering design, manufacturing, shipping documentation, installation supervision, commissioning, operator training, warranty and spare parts.
Typical programme
The durations below are typical for equipment of this class and are given for planning; they are not the recorded schedule of this project. A complete line usually runs 90–180 days from contract to acceptance, a single unit 30–60 days.
| Stage | Typical duration | What happens |
|---|---|---|
| Site survey and workpiece review | 5–10 days | Remote review of drawings and photos, or an engineer visit |
| Layout and detail design | 15–30 days | Layout drawing, utilities list and specification sign-off |
| Manufacturing | 45–90 days | Booths, ovens, conveyor, pretreatment and controls built and pre-assembled at the works |
| Shipping | 20–45 days | Sea freight; equipment shipped in sections for on-site assembly |
| Installation | 15–40 days | MUSI supervision with the client's installation crew or MUSI crew |
| Commissioning, training and acceptance | 7–15 days | Trial runs on the client's parts, operator training, acceptance record |
Results: before and after
Figures are those published on this page; measurement party, sample size, test date and method are not on record here and are left blank rather than estimated.
| Metric | Before | After | Change | Measured by | Single / average | Samples | Test date | Method / instrument |
|---|---|---|---|---|---|---|---|---|
| Labour | 4 dispersed areas | −40% | −40% | |||||
| Energy | 4 dispersed areas | −28% | −28% | |||||
| Capacity | 4 dispersed areas | +50% | +50% | |||||
| Delivery | — | 6 months, on schedule | — |
Applicability and limits
The labour, energy and capacity gains come from consolidating four dispersed areas into one designed workshop; a plant that already runs a single line will not see the same percentages. EPC delivery in six months depended on early permits and a site office; where permits take longer the schedule moves with them.
Results shown in this case study reflect the stated operating conditions and should not be interpreted as guaranteed performance under different feed, production, environmental, or site conditions.
After-sales and spare parts
Warranty on a MUSI coating line runs from acceptance: 12 months on the complete line excluding consumables, 36 months on critical components such as motors, drives and the PLC, and 60 months on structural parts such as steel structure, ducting and oven bodies. Failures within warranty, excluding misuse, are repaired free of charge.
Support starts remotely: the service line is staffed around the clock, a preliminary diagnosis with recommendations is given within 2 hours, and where a site visit is needed an engineer reaches any major city within 72 hours. A spare-parts inventory is held at the Changzhou headquarters with same-day shipping, and customers can keep a dedicated parts stock at MUSI for emergencies. Details are on the after-sales service page.
FAQ
What does EPC mean for a coating workshop? MUSI takes design, procurement, construction and commissioning under one contract, including civil, HVAC, fire and environmental works, and hands over a running workshop.
How long does a turnkey coating workshop take? Six months here: two months of design and permits, three months of manufacturing and construction, one month of commissioning.
Why five booths and five ovens? Mining equipment parts span small brackets to large welded structures with different coating systems and cure profiles, so parallel stations keep each family on its own process.
What were the measured gains? Consolidation reduced labour by 40% and energy by 28% and increased capacity by 50% against the four old areas, on the client's figures.
How was the site managed? A MUSI project office on site ran daily briefings, weekly plans and monthly milestones for up to eight trades working at once.
Next step: a configuration proposal for a similar line
If your parts, volumes or plant conditions are close to this project, MUSI can return a line configuration and layout proposal. To prepare it we need four things:
- Photos and dimensions of the workpieces, with weight and material
- Required output (pieces per hour or per day, and shifts)
- Number of colours and how often colour changes are needed
- Available floor space and ceiling height, with the utilities on site
Message us on WhatsApp with these details, or use the quotation form.
Provided by Lin Cong, Technical Director, MUSI Technology · Published 2026-05-02 · Updated 2026-09-30 · Last technical review: 2026-09-30
QQuestions buyers ask before ordering
quotation · price · lead time · installation · warranty
What information do you need to prepare a quotation?
Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.
How much does this equipment cost?
Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our complete coating line cost guide; a configured quotation is prepared from your part data. Published indicative ex-works ranges: a complete powder coating line is roughly USD 75,000–230,000 semi-automatic, USD 200,000–600,000 for a standard automatic line and USD 600,000–2,000,000 for a high-throughput automated plant.
What is the lead time?
Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.
Do you install and train operators overseas?
Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.
What warranty and after-sales support are included?
12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.
Can the environmental equipment be supplied with the line?
Yes. VOC treatment (RTO, RCO, activated carbon, zeolite rotor), dust collection and paint wastewater treatment are supplied with the coating line under one contract; MUSI has equipped 50+ coating facilities whose projects all passed local environmental compliance reviews.