Construction Equipment Coating Workshop
CASE STUDY · 2023

Case Study: Construction Equipment Coating Workshop

  • IndustryHeavy Machinery
  • Year2023
  • LocationRussia
  • Scale12×6×5 m booth, 200 pcs/month
Heavy PartsHeavy-Duty Anti-CorrosionSalt Spray 2000h
Request Similar Solution Back to Cases

Summary

A large-part liquid coating workshop for a supplier of excavator booms and loader chassis to a major construction-machinery OEM in Russia, built around a 12 × 6 × 5 m spray booth with 60,000 m³/h filtered air supply and a matching 12 × 6 × 5 m forced-hot-air drying booth. Parts up to 10 × 4 × 4 m and 8 tonnes receive an epoxy primer, epoxy intermediate and polyurethane topcoat, and the coating reached 2,400 hours in salt spray against a 2,000-hour OEM target. Capacity is 200 large structural parts per month. Test results as reported at OEM coating certification in 2023.

Project Background

The client is a key supplier to a major construction machinery OEM in Russia, producing excavator booms and loader chassis. Their existing coating facility was outdated and could not meet the OEM's new coating durability requirements.

The Challenge

Construction machinery components weigh 3-8 tons and reach 12 m long — beyond the capacity of standard coating equipment. Outdoor working environments are severe, demanding heavy-duty anti-corrosion coatings that pass 2,000-hour salt spray.

MUSI's Solution

MUSI engineered a custom large-scale automatic spray booth: 12×6×5 m standard booth, with drive-through doors for forklift access, three-stage filtration + 60,000 m³/h forced air supply, paired with primer-intermediate-topcoat triple-layer heavy-duty anti-corrosion system.

Equipment Configuration

Booth size12×6×5 m (L×W×H)
Max workpiece12×4×4 m, weight ≤8 tons
Air supply60,000 m³/h
FiltrationPre-filter G4 + medium F7 + ceiling F9
Coating systemEpoxy primer + epoxy intermediate + polyurethane topcoat
Drying booth12×6×5 m forced hot air
EnvironmentalActivated carbon adsorption + catalytic combustion
Monthly capacity200 large structural parts

Implementation

110-day project including foundation civil works + steel structure + equipment install + commissioning. Modular pre-fabrication + on-site assembly approach shortened schedule.

Results

Coating salt spray reached 2,400 hours (target 2,000 h), passing OEM coating certification. The client secured stable orders from major Russian and CIS construction equipment OEMs, with annual revenue exceeding $17 M USD.

Client Feedback

"Construction machinery coating standards keep getting tougher every year. MUSI helped us reach the highest OEM standard in one step — our biggest gain."
— Project Manager, Client Side

Selection logic: why this configuration

A drive-through booth with forklift access was chosen over a conveyorised line because parts of 3–8 tonnes and up to 12 m are moved more safely on transport frames than on hangers, and monthly volume of 200 parts does not justify a conveyor. Three-stage filtration (G4, F7, F9) was specified because a topcoat on a boom is inspected by the OEM for inclusions. Activated carbon with catalytic combustion was preferred to an RTO because the booth runs intermittently.

Scope of supply and key components

ItemSpecificationNotes
Spray booth12 × 6 × 5 m, drive-through doorsParts to 10 × 4 × 4 m, 8 t
Air supply60,000 m³/h, G4 + F7 + F9 filtration
Drying booth12 × 6 × 5 m forced hot air
Coating systemEpoxy primer, epoxy intermediate, polyurethane topcoatPaint supplied by the client
VOC treatmentActivated carbon adsorption + catalytic combustion
Civil and steelFoundations and steel structureIncluded in this project as turnkey

Key components

Key components are available from international brands, configurable per customer specification, so that spare parts can be sourced locally over the life of the line. Brand names below are the usual options for this type of equipment; the brands actually fitted are fixed in the contract specification.

ComponentBrands available on request
Automatic liquid guns, pumps and 2K proportionersInternational tier-one spray gun, pump and 2K proportioner brands
Booth ceiling and intake filter mediaFreudenberg Viledon, AAF SureStop, Camfil, MANN+HUMMEL
Oven and dryer gas burnersRiello RS series, Weishaupt monarch WM-G, Baltur TBG, Honeywell Maxon OVENPAK, Eclipse
PLC and HMISiemens SIMATIC S7-1500, Mitsubishi Electric MELSEC iQ-R, Schneider Electric Modicon, OMRON NX, Rockwell Automation Allen-Bradley
Variable-frequency drivesABB ACS580, Siemens SINAMICS G120, Danfoss VLT, Schneider Electric Altivar, Yaskawa, Mitsubishi Electric
RTO ceramic media and burnersLantec MLM, Honeywell Maxon line burners, Riello RS, Eclipse
Sensors and temperature controllersSICK, Pepperl+Fuchs, OMRON E5CC, Honeywell UDC, Yokogawa UT, ifm, KEYENCE
Compressed air for powder feed and instrumentsAtlas Copco GA, Ingersoll Rand RS, KAESER ASD, Sullair

Not included in the scope of supply

  • Building services up to the battery limit: power supply, gas, compressed air, water and drainage
  • Local permits, emission approvals and third-party inspections
  • Paint or powder supply, unless stated in the contract
  • Paint and thinner supply

Services included with every line: engineering design, manufacturing, shipping documentation, installation supervision, commissioning, operator training, warranty and spare parts.

Typical programme

The durations below are typical for equipment of this class and are given for planning; they are not the recorded schedule of this project. A complete line usually runs 90–180 days from contract to acceptance, a single unit 30–60 days.

StageTypical durationWhat happens
Site survey and workpiece review5–10 daysRemote review of drawings and photos, or an engineer visit
Layout and detail design15–30 daysLayout drawing, utilities list and specification sign-off
Manufacturing45–90 daysBooths, ovens, conveyor, pretreatment and controls built and pre-assembled at the works
Shipping20–45 daysSea freight; equipment shipped in sections for on-site assembly
Installation15–40 daysMUSI supervision with the client's installation crew or MUSI crew
Commissioning, training and acceptance7–15 daysTrial runs on the client's parts, operator training, acceptance record

Results: before and after

Figures are those published on this page; measurement party, sample size, test date and method are not on record here and are left blank rather than estimated.

MetricBeforeAfterChangeMeasured bySingle / averageSamplesTest dateMethod / instrument
Neutral salt spray2,000 h OEM target2,400 h+400 h over target

Applicability and limits

The 2,400-hour salt-spray result applies to blast-cleaned steel with the three-coat epoxy-polyurethane system applied in a controlled booth. Plants that skip blast cleaning or apply a single coat will not reach the same figure, and the booth size given here is sized for booms and chassis rather than complete machines.

Results shown in this case study reflect the stated operating conditions and should not be interpreted as guaranteed performance under different feed, production, environmental, or site conditions.

After-sales and spare parts

Warranty on a MUSI coating line runs from acceptance: 12 months on the complete line excluding consumables, 36 months on critical components such as motors, drives and the PLC, and 60 months on structural parts such as steel structure, ducting and oven bodies. Failures within warranty, excluding misuse, are repaired free of charge.

Support starts remotely: the service line is staffed around the clock, a preliminary diagnosis with recommendations is given within 2 hours, and where a site visit is needed an engineer reaches any major city within 72 hours. A spare-parts inventory is held at the Changzhou headquarters with same-day shipping, and customers can keep a dedicated parts stock at MUSI for emergencies. Details are on the after-sales service page.

FAQ

How big a part can a spray booth like this take? Parts up to 10 × 4 × 4 m and 8 tonnes in this 12 × 6 × 5 m booth, moved in on transport frames by forklift through the drive-through doors.

Why three filter stages on the air supply? A G4 pre-filter protects the F7 stage, and the F9 ceiling filter keeps particles out of the topcoat, which the OEM inspects for inclusions on visible faces.

Is a conveyor needed for heavy machinery parts? Not at 200 parts a month. Below roughly 30 parts a day a batch booth with forklift or transfer-cart handling is simpler and safer than hanging 8-tonne parts.

What coating system reaches 2,000 hours salt spray? On this project, epoxy primer, epoxy intermediate and polyurethane topcoat over blast-cleaned steel; it tested at 2,400 hours.

Was civil work part of the delivery? Yes, this project included foundations, steel structure, equipment and commissioning in a 110-day programme using modular prefabrication and on-site assembly.

Next step: a configuration proposal for a similar line

If your parts, volumes or plant conditions are close to this project, MUSI can return a line configuration and layout proposal. To prepare it we need four things:

  • Photos and dimensions of the workpieces, with weight and material
  • Required output (pieces per hour or per day, and shifts)
  • Number of colours and how often colour changes are needed
  • Available floor space and ceiling height, with the utilities on site

Message us on WhatsApp with these details, or use the quotation form.

Provided by Lin Cong, Technical Director, MUSI Technology · Published 2026-05-02 · Updated 2026-09-30 · Last technical review: 2026-09-30

Q

Questions buyers ask before ordering

quotation · price · lead time · installation · warranty

What information do you need to prepare a quotation?

Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.

How much does this equipment cost?

Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our complete coating line cost guide; a configured quotation is prepared from your part data. Published indicative ex-works ranges: a complete powder coating line is roughly USD 75,000–230,000 semi-automatic, USD 200,000–600,000 for a standard automatic line and USD 600,000–2,000,000 for a high-throughput automated plant.

What is the lead time?

Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.

Do you install and train operators overseas?

Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.

What warranty and after-sales support are included?

12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.

Can the environmental equipment be supplied with the line?

Yes. VOC treatment (RTO, RCO, activated carbon, zeolite rotor), dust collection and paint wastewater treatment are supplied with the coating line under one contract; MUSI has equipped 50+ coating facilities whose projects all passed local environmental compliance reviews.