Operators spray-painting steel panels in front of a corrugated dry filter wall inside a spray booth
CASE STUDY · 2025

Case Study: Telescopic Spray Booth for Crane Girder Painting, Mexico

  • ClientOverhead crane and gantry manufacturer (name withheld)
  • IndustryCrane Manufacturing
  • Year2025
  • LocationMexico
  • Scale20 x 10 x 4 m dry-filter telescopic booth
North AmericaCrane GirdersTelescopic BoothMexico
Request Similar Solution Back to Cases

Summary

ObjectCrane girders up to 20 m and end carriages for a Overhead crane and gantry manufacturer in Mexico
Equipment20 x 10 x 4 m dry-filter telescopic booth
Operating conditionscrane-handled batch painting, dry filter wall: labyrinth paper filters plus glass-fibre bags, cross-draft 0.3 m/s or more
ResultGirders painted in the assembly bay without moving them to another building
Sourceproject specification and commissioning scope; client name withheld at the client's request
Delivery record800+ coating lines for 500+ clients in 36 countries (MUSI engineering team, cumulative since 2011)
ServicesDesign, manufacturing, installation, commissioning, operator training and after-sales support from one company

Project Background

A Mexican manufacturer of overhead cranes and gantries fabricated box girders up to 20 m for automotive and steel plants. Girders were painted in the assembly bay with the plant's own cranes, and the plant needed an enclosure that would not block the runway above.

Pain Points Before the Project

  • 20 m box girders with no booth long enough
  • Crane runway could not be interrupted
  • Customer liveries with frequent colour changes
  • Local air permit required enclosed painting with treatment

Why This Configuration Was Chosen

  • A 20 x 10 x 4 m telescopic booth on floor rails, no fixed roof, so the runway stays clear
  • Dry filtration suits frequent colour changes; filters are the only overspray-contact surface
  • Carbon boxes with UV pre-oxidation and a 75 kW fan sized at 0.3 m/s or more

Scope of Supply

Telescopic enclosure20 x 10 x 4 m internal (retracted about 3 x 10.7 m); Q235 frames 50 x 70 x 2 mm, flame-retardant PVC fabric
Drive and safety2 x 1.5 kW explosion-proof geared motors, 8-10 m/min; interlocked drives, double limit switches, rail sweeper, jog control
Lighting60 explosion-proof LED units, 18 W each, 300 lux or more
Paint mist captureDry filter wall: labyrinth paper filters plus glass-fibre bags, 98% or more mist capture
Exhaust treatmentActivated carbon boxes plus UV photo-oxidation unit, 50,000 m3/h class
Fan, duct and stack75 kW centrifugal fan, 54,000-79,400 m3/h, 15 m stack
ControlTwo-station control cabinet, VFD on exhaust fan, emergency stop, audible-visual travel alarm
Installed powerabout 109 kW installed

Component brands. Key components are sourced from international first-tier brands at the client's choice; the table lists the options offered on this project.

ComponentBrand options
Exhaust fanNicotra Gebhardt, Kruger, Systemair
Geared drive motorsSEW-Eurodrive, NORD, Bonfiglioli
Explosion-proof lightingEaton Crouse-Hinds, R. STAHL, ABB
Low-voltage switchgearSchneider Electric, Siemens, ABB
Variable frequency driveABB, Danfoss, Siemens
PLC (RCO control)Siemens, Mitsubishi Electric, Omron
Filter mediaAndreae Filters, Freudenberg Viledon, Camfil
Activated carbonCalgon Carbon, Jacobi Carbons, Cabot Norit
Oxidation catalystBASF, Johnson Matthey, Clariant
Flame-retardant fabricSerge Ferrari, Sioen, Mehler Texnologies
Flexible cablesLAPP, Nexans, Prysmian
Airless spray units (client side)International tier-one spray gun brands

Not included: rail levelling and civil foundations, site lifting, third-party emission testing, workpiece stands unless ordered, and the drying room where forced cure is required.

Programme

Typical programme for this booth class; the dates for each project are fixed in the contract.

StageTypical duration
Site survey and data collection3-7 days
Layout and detail design10-15 days
Manufacture and factory trial30-45 days
Sea freight and customs15-40 days
Rail levelling by site, installation7-14 days
Commissioning, emission test, training3-5 days

Before and After

Design values from the project specification; the "before" column describes the open-floor condition found at survey, for which no measurements existed.

ItemBeforeAfter
Enclosure of the painting areaopen bay or shed, no enclosuretelescopic booth, 20 x 10 x 4 m
Floor available when not paintingpainting area blocked or sharedbooth retracted, about 85% of footprint freed
Cross-draft over the worknot controlled0.3 m/s or more (design)
Paint mist capturenone98% or more (design)
VOC treatment efficiencynone85-90% (carbon) with UV pre-oxidation (design)
Lighting at the work surfaceworkshop lighting300 lux or more, explosion-proof (design)
Noise inside the boothnot controlled80 dB(A) or less (design)

Results

  • Girders painted in the assembly bay without moving them to another building
  • Colour changes between liveries without cleaning a water circuit
  • Booth retracted to about 3 m between paint batches

Applicability

This configuration suits workshops where the crane moves the workpiece, painting is done in batches and the floor must return to assembly use between batches: structural steel, vessels and tanks, machinery frames, crane girders, trailer chassis and hull blocks. It is not the right choice for conveyorised lines painting every shift, for coatings that need forced cure inside the same enclosure, or where a water-curtain booth and water treatment already exist.

The results above apply to the configuration and conditions described. A different part mix, paint system, climate or emission limit changes the numbers, which is why every booth is sized from its own data.

After-Sales

Warranty options of 12, 36 or 60 months, remote diagnosis within 2 hours and on-site attendance within 72 hours where a local partner is available, plus filter media, carbon and catalyst supply for the life of the booth. Details are on our after-sales service page.

FAQ

Can the same booth paint different products?

Yes. Nothing in the enclosure is shaped to the part; the booth on this project handled the full range of crane girders.

Why was dry capture chosen here?

Intermittent painting and frequent colour changes favour dry labyrinth-paper filtration: no water or oil circuit, and the filter wall is the only overspray-contact surface.

What did the client have to prepare?

Levelled rails to our drawing, a concrete pad for the fan and treatment unit, three-phase power to the cabinet and a crane for installation.

How was performance checked?

Travel and limit switches in both directions, drive interlock, cross-draft velocity, lighting level, noise, and stack sampling against the local limit.

Can this booth be extended later?

Frames are added in 1 m modules and the rails extended; the fan and filter wall are sized for the final length at the outset.

Get a Similar Solution

Send us the following and we return a booth layout with fan, filter and treatment sizing within a few working days:

  • Largest workpiece length, width, height and weight, and how it is handled
  • Daily paint and thinner consumption and the paint system
  • Indoor or outdoor installation, crane hook height and available floor
  • Local emission limit and workplace exposure rule

WhatsApp us about this case Contact form

Related

Provided by Lin Cong, Technical Director, MUSI Technology
Published 2026-10-01 · Updated 2026-10-01 · Last technical review: 2026-10-01

Q

Questions buyers ask before ordering

quotation · price · lead time · installation · warranty

What information do you need to prepare a quotation?

Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.

How much does this equipment cost?

Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our complete coating line cost guide; a configured quotation is prepared from your part data. Published indicative ex-works ranges: a complete powder coating line is roughly USD 75,000–230,000 semi-automatic, USD 200,000–600,000 for a standard automatic line and USD 600,000–2,000,000 for a high-throughput automated plant.

What is the lead time?

Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.

Do you install and train operators overseas?

Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.

What warranty and after-sales support are included?

12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.

Can the environmental equipment be supplied with the line?

Yes. VOC treatment (RTO, RCO, activated carbon, zeolite rotor), dust collection and paint wastewater treatment are supplied with the coating line under one contract; MUSI has equipped 50+ coating facilities whose projects all passed local environmental compliance reviews.