Overhead conveyor entering a spray booth
CASE STUDY · 2026

Case Study: Truck Parts Coating Line, Vietnam

  • ClientAssembly plant of a Chinese automaker
  • IndustryAutomotive Parts
  • Year2026
  • LocationVietnam
  • ScaleTruck and commercial vehicle parts
Vehicle AssemblyTruck PartsVietnam
Request Similar Solution Back to Cases

Summary

A coating line for truck parts at a plant in Binh Duong province, Vietnam, that assembles a Chinese automaker's light, medium and heavy trucks, tractor units, special-purpose vehicles and buses from CKD and IKD kits. The line is an overhead conveyor with a pumped pretreatment section and its own control cabinet feeding parts straight into the spray booth and curing oven, so cleaned parts are coated without re-handling, with exhaust treatment included. The line coats truck and commercial vehicle parts in 2026.

Project Background

The client assembles a Chinese automaker’s light, medium and heavy trucks, tractor units, special-purpose vehicles and buses in Binh Duong province, near Ho Chi Minh City, from CKD and IKD kits. MUSI supplied a coating line for truck parts.

The plant is a joint venture with the JAC brand's Vietnamese partners and assembles JAC light and medium trucks from CKD and IKD kits.

The Challenge

Truck parts come in many shapes and sizes, from brackets to large panels, and they work in heat, humidity and heavy rain. Coating quality depends on clean steel, so pretreatment has to be controlled as tightly as the spraying itself.

MUSI's Solution

MUSI supplied an overhead conveyor coating line with a pumped pretreatment section and its own control cabinet, feeding parts straight into the spray booth and curing, so cleaned parts are coated without re-handling.

Pretreatment tank pumps and control cabinet
Pretreatment tank pumps and control cabinet

Equipment Scope

  • Pretreatment tanks with pumps and control cabinet
  • Overhead conveyor
  • Spray booth
  • Curing oven
  • Exhaust treatment

Results

The line coats truck and commercial vehicle parts for the client’s assembly operation in Vietnam.

Selection logic: why this configuration

A pumped pretreatment section with its own control cabinet was placed at the head of the line because in Vietnam's heat and humidity the interval between cleaning and coating is where flash rust starts; parts go from the last rinse to the booth on the same conveyor. An overhead conveyor was chosen because truck parts range from brackets to panels and all hang.

Scope of supply and key components

ItemSpecificationNotes
PretreatmentTanks with pumps and control cabinet
Overhead conveyor
Spray booth
Curing oven
Exhaust treatment

Key components

Key components are available from international brands, configurable per customer specification, so that spare parts can be sourced locally over the life of the line. Brand names below are the usual options for this type of equipment; the brands actually fitted are fixed in the contract specification.

ComponentBrands available on request
Pretreatment pumps and chemistryGrundfos CR, KSB Etanorm, Xylem; Henkel BONDERITE, Chemetall Gardobond, PPG Zircobond, Nippon Paint
Automatic liquid guns, pumps and 2K proportionersInternational tier-one spray gun, pump and 2K proportioner brands
Automatic powder guns and powder feedInternational tier-one powder spray gun brands
Oven and dryer gas burnersRiello RS series, Weishaupt monarch WM-G, Baltur TBG, Honeywell Maxon OVENPAK, Eclipse
PLC and HMISiemens SIMATIC S7-1500, Mitsubishi Electric MELSEC iQ-R, Schneider Electric Modicon, OMRON NX, Rockwell Automation Allen-Bradley
Variable-frequency drivesABB ACS580, Siemens SINAMICS G120, Danfoss VLT, Schneider Electric Altivar, Yaskawa, Mitsubishi Electric
Conveyor gear motorsSEW-EURODRIVE, NORD DRIVESYSTEMS, Bonfiglioli, Siemens, Sumitomo Drive Technologies
Sensors and temperature controllersSICK, Pepperl+Fuchs, OMRON E5CC, Honeywell UDC, Yokogawa UT, ifm, KEYENCE

Not included in the scope of supply

  • Civil works, foundations and pits
  • Building services up to the battery limit: power supply, gas, compressed air, water and drainage
  • Local permits, emission approvals and third-party inspections
  • Paint or powder supply, unless stated in the contract

Services included with every line: engineering design, manufacturing, shipping documentation, installation supervision, commissioning, operator training, warranty and spare parts.

Typical programme

The durations below are typical for equipment of this class and are given for planning; they are not the recorded schedule of this project. A complete line usually runs 90–180 days from contract to acceptance, a single unit 30–60 days.

StageTypical durationWhat happens
Site survey and workpiece review5–10 daysRemote review of drawings and photos, or an engineer visit
Layout and detail design15–30 daysLayout drawing, utilities list and specification sign-off
Manufacturing45–90 daysBooths, ovens, conveyor, pretreatment and controls built and pre-assembled at the works
Shipping20–45 daysSea freight; equipment shipped in sections for on-site assembly
Installation15–40 daysMUSI supervision with the client's installation crew or MUSI crew
Commissioning, training and acceptance7–15 daysTrial runs on the client's parts, operator training, acceptance record

Applicability and limits

The line is sized for the range of truck parts hung on one conveyor; large cabs or complete frames need a separate line. Humidity control in the booth and pretreatment dry-off is site-specific and follows the humidity guide linked below.

Results shown in this case study reflect the stated operating conditions and should not be interpreted as guaranteed performance under different feed, production, environmental, or site conditions.

After-sales and spare parts

Warranty on a MUSI coating line runs from acceptance: 12 months on the complete line excluding consumables, 36 months on critical components such as motors, drives and the PLC, and 60 months on structural parts such as steel structure, ducting and oven bodies. Failures within warranty, excluding misuse, are repaired free of charge.

Support starts remotely: the service line is staffed around the clock, a preliminary diagnosis with recommendations is given within 2 hours, and where a site visit is needed an engineer reaches any major city within 72 hours. A spare-parts inventory is held at the Changzhou headquarters with same-day shipping, and customers can keep a dedicated parts stock at MUSI for emergencies. Details are on the after-sales service page.

Who installed this line?

This line was installed and commissioned on site by MUSI engineers. Other lines MUSI engineers have installed on site are listed on the installation and commissioning page.

FAQ

How is flash rust avoided in a humid climate? By keeping the time between the last rinse and the booth short on one conveyor, with a dry-off stage sized for the humidity, and by controlling the pretreatment chemistry from its own cabinet.

What parts run on the line? Truck and commercial vehicle parts from brackets to panels, hung on the overhead conveyor.

Why does the pretreatment have its own control cabinet? So pump operation, temperatures and dosing are controlled and logged independently of the conveyor, which is what keeps cleaning consistent.

What vehicles does the plant assemble? JAC light and medium trucks and related commercial vehicles, from CKD and IKD kits, at the joint-venture plant in Binh Duong.

Is the line running? Yes, coating truck and commercial vehicle parts for the assembly operation.

Next step: a configuration proposal for a similar line

If your parts, volumes or plant conditions are close to this project, MUSI can return a line configuration and layout proposal. To prepare it we need four things:

  • Photos and dimensions of the workpieces, with weight and material
  • Required output (pieces per hour or per day, and shifts)
  • Number of colours and how often colour changes are needed
  • Available floor space and ceiling height, with the utilities on site

Message us on WhatsApp with these details, or use the quotation form.

Published 2026-09-26 · Updated 2026-09-30 · Last technical review: 2026-09-30

Q

Questions buyers ask before ordering

quotation · price · lead time · installation · warranty

What information do you need to prepare a quotation?

Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.

How much does this equipment cost?

Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our complete coating line cost guide; a configured quotation is prepared from your part data. Published indicative ex-works ranges: a complete powder coating line is roughly USD 75,000–230,000 semi-automatic, USD 200,000–600,000 for a standard automatic line and USD 600,000–2,000,000 for a high-throughput automated plant.

What is the lead time?

Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.

Do you install and train operators overseas?

Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.

What warranty and after-sales support are included?

12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.

Can the environmental equipment be supplied with the line?

Yes. VOC treatment (RTO, RCO, activated carbon, zeolite rotor), dust collection and paint wastewater treatment are supplied with the coating line under one contract; MUSI has equipped 50+ coating facilities whose projects all passed local environmental compliance reviews.

Request a configured quotationWhatsApp +86 181 5173 1332 · lin@coating-spray.com

Get a Similar Solution

If your industry and requirements match this case, contact MUSI to schedule a free consultation. We'll design an optimal solution based on your specific workpieces, capacity, and facility.

Provided by Lin Cong, Technical Director, MUSI Technology