Stainless steel powder booth and powder gun unit
CASE STUDY · 2026

Case Study: Electrical Products Spray Coating Line, Bangladesh

  • ClientElectrical products and hardware manufacturer
  • IndustryMetal Hardware
  • Year2026
  • LocationBangladesh
  • ScaleAutomatic spray coating line, about 7.8 t of equipment
Electrical ProductsAutomatic SprayingExport
Request Similar Solution Back to Cases

Summary

An automatic spray coating line, about 7.8 tonnes of equipment, for a Dhaka manufacturer of switchgear, lighting fixtures, locks and electrical accessories with its own metal stamping, electroplating, plastic moulding and surface painting. The line gives film build and appearance that depend on equipment settings rather than on the operator, with an automatic spray booth and guns, conveyor, curing section and exhaust with overspray treatment, shipped from China in June 2026.

Project Background

The client, based in Dhaka, manufactures switchgear, lighting fixtures, locks and electrical accessories, with its own metal stamping, electroplating, plastic moulding and surface painting. MUSI supplied an automatic spray coating production line, shipped from China in June 2026.

The Challenge

Electrical products combine many small metal and plastic parts that all need the same colour and finish, in a hot and humid climate where coating quality is easily affected by moisture. Manual spraying makes that consistency hard to hold.

MUSI's Solution

MUSI supplied an automatic spray coating line so that film build and appearance depend on equipment settings rather than on the operator, with the parts carried through spraying and curing on one conveyor.

Spray coating line for electrical parts
Spray coating line for electrical parts

Equipment Scope

  • Automatic spray booth and spray guns
  • Conveyor system
  • Curing section
  • Exhaust and overspray treatment

Results

The line was shipped in June 2026, adding automated spraying to the client’s in-house surface finishing.

Selection logic: why this configuration

An automatic booth on a conveyor was chosen over upgrading the client's manual spraying because electrical products combine many small metal and plastic parts that must match in colour, and manual work in a hot, humid climate does not hold that consistency. The line was kept compact, at about 7.8 tonnes, to fit an existing finishing department.

Scope of supply and key components

ItemSpecificationNotes
Spray boothAutomatic booth and spray guns
Conveyor
Curing section
Exhaust and overspray treatment

Key components

Key components are available from international brands, configurable per customer specification, so that spare parts can be sourced locally over the life of the line. Brand names below are the usual options for this type of equipment; the brands actually fitted are fixed in the contract specification.

ComponentBrands available on request
Automatic liquid guns, pumps and 2K proportionersGraco ProMix 2KS, Sames Airmix, WAGNER AirCoat, Nordson, Binks (Carlisle Fluid Technologies)
Automatic powder guns and powder feedGema OptiGun, Nordson Encore, WAGNER PEA-X1, Sames (formerly SAMES KREMLIN)
PLC and HMISiemens SIMATIC S7-1500, Mitsubishi Electric MELSEC iQ-R, Schneider Electric Modicon, OMRON NX, Rockwell Automation Allen-Bradley
Variable-frequency drivesABB ACS580, Siemens SINAMICS G120, Danfoss VLT, Schneider Electric Altivar, Yaskawa, Mitsubishi Electric
Conveyor gear motorsSEW-EURODRIVE, NORD DRIVESYSTEMS, Bonfiglioli, Siemens, Sumitomo Drive Technologies
Booth ceiling and intake filter mediaFreudenberg Viledon, AAF SureStop, Camfil, MANN+HUMMEL
Dust collector filter cartridgesDonaldson Ultra-Web, Parker BHA, Camfil, MANN+HUMMEL
Compressed air for powder feed and instrumentsAtlas Copco GA, Ingersoll Rand RS, KAESER ASD, Sullair

Not included in the scope of supply

  • Civil works, foundations and pits
  • Building services up to the battery limit: power supply, gas, compressed air, water and drainage
  • Local permits, emission approvals and third-party inspections
  • Paint or powder supply, unless stated in the contract
  • Installation labour and site utilities at the Dhaka plant

Services included with every line: engineering design, manufacturing, shipping documentation, installation supervision, commissioning, operator training, warranty and spare parts.

Typical programme

The durations below are typical for equipment of this class and are given for planning; they are not the recorded schedule of this project. A complete line usually runs 90–180 days from contract to acceptance, a single unit 30–60 days.

StageTypical durationWhat happens
Site survey and workpiece review5–10 daysRemote review of drawings and photos, or an engineer visit
Layout and detail design15–30 daysLayout drawing, utilities list and specification sign-off
Manufacturing45–90 daysBooths, ovens, conveyor, pretreatment and controls built and pre-assembled at the works
Shipping20–45 daysSea freight; equipment shipped in sections for on-site assembly
Installation15–40 daysMUSI supervision with the client's installation crew or MUSI crew
Commissioning, training and acceptance7–15 daysTrial runs on the client's parts, operator training, acceptance record

Applicability and limits

The line is sized for small electrical parts on one conveyor; large panels or enclosures would need a bigger booth and oven. Shipment date is from the shipping records; production figures at the plant have not been published.

Results shown in this case study reflect the stated operating conditions and should not be interpreted as guaranteed performance under different feed, production, environmental, or site conditions.

After-sales and spare parts

Warranty on a MUSI coating line runs from acceptance: 12 months on the complete line excluding consumables, 36 months on critical components such as motors, drives and the PLC, and 60 months on structural parts such as steel structure, ducting and oven bodies. Failures within warranty, excluding misuse, are repaired free of charge.

Support starts remotely: the service line is staffed around the clock, a preliminary diagnosis with recommendations is given within 2 hours, and where a site visit is needed an engineer reaches any major city within 72 hours. A spare-parts inventory is held at the Changzhou headquarters with same-day shipping, and customers can keep a dedicated parts stock at MUSI for emergencies. Details are on the after-sales service page.

FAQ

How is colour kept consistent across metal and plastic parts? By automatic spraying with fixed gun settings and conveyor speed, so every part receives the same film regardless of the operator, and by curing both substrates within their temperature limits.

Does humidity affect coating quality? Yes; moisture in the booth air and on parts causes blushing and adhesion faults. Controlled booth air and a short interval from cleaning to spraying reduce it.

What was shipped? About 7.8 tonnes of equipment in June 2026: automatic booth and guns, conveyor, curing section and exhaust treatment.

Can the line coat both powder and liquid? The line is configured for the coating system the client specified; guns for the other system can be added if the booth and cure are compatible.

Where does the client use the line? In its in-house surface finishing for switchgear, lighting fixtures, locks and electrical accessories.

Next step: a configuration proposal for a similar line

If your parts, volumes or plant conditions are close to this project, MUSI can return a line configuration and layout proposal. To prepare it we need four things:

  • Photos and dimensions of the workpieces, with weight and material
  • Required output (pieces per hour or per day, and shifts)
  • Number of colours and how often colour changes are needed
  • Available floor space and ceiling height, with the utilities on site

Message us on WhatsApp with these details, or use the quotation form.

Published 2026-09-26 · Updated 2026-09-30 · Last technical review: 2026-09-30

Get a Similar Solution

If your industry and requirements match this case, contact MUSI to schedule a free consultation. We'll design an optimal solution based on your specific workpieces, capacity, and facility.

Provided by Lin Cong, Technical Director, MUSI Technology