Automotive Wheel Hub Powder Coating Line
CASE STUDY · 2024

Automotive Wheel Hub Powder Coating Line

  • IndustryAutomotive Parts
  • Year2024
  • LocationTurkey
  • Scale12-sec cycle, 2 million/year
AutoWheel HubsPowder Coating
Request Similar Solution Back to Cases

Summary

A dedicated wheel-hub powder coating line for an automotive wheel supplier in Turkey that supplies Renault Turkey, Ford Otosan and other regional OEMs, built for 2 million hubs a year at 12 seconds per hub and IATF 16949 process requirements. Hubs rotate 360° on fixtures past 18 guns (12 circumferential, 4 side, 2 face) and cure at 200 °C, film build is 70 ± 10 μm, and the line runs fully automatic loading, spraying and curing at 6,000 hubs per day on two shifts. The line ramped to full capacity in six months and passed the OEM audit at the first attempt, as reported after commissioning in 2024.

Project Background

The client is a known automotive wheel hub supplier in Turkey, supplying Renault Turkey, Ford Otosan, and other regional OEMs. Their new factory required high cycle (annual 2 million pieces) and high quality (IATF 16949 compliance).

The Challenge

Auto wheel hubs have complex structure (spokes, rim, decorative face) with many spray dead zones. 2-million-piece annual capacity means cycle time must be controlled within 12 seconds/piece.

MUSI's Solution

MUSI designed a dedicated wheel hub coating line: load → rotating fixture → 12 circumferential guns + 4 side guns + 2 face guns → 200 °C cure. Workpieces rotate 360° during spray for uniform coverage.

Equipment Configuration

Line typeOverhead chain wheel hub coating
Fixture360° rotating workpiece fixture
Spray gun layoutCircumferential 12 + side 4 + face 2 = 18 guns
Cycle time12 sec/piece
Daily capacity6,000 pieces (2 shifts)
Annual capacity2 million pieces
Film thickness70±10 μm
AutomationFull auto load/spray/cure

Implementation

100-day delivery. During construction, MUSI engineers stayed on-site to assist new factory's coating workshop layout — including pits, structural steel, electrical coordination.

Results

After commissioning, the line ramped to full capacity in 6 months. OEM audit passed first attempt. The client gained 2 new OEM clients in the same year, doubling annual revenue.

Client Feedback

"MUSI provided more than equipment — they participated in our entire factory planning. This 'one-stop' service saved us from many detours."
— Project Manager, Client Side

Selection logic: why this configuration

A rotating-fixture line with fixed guns was chosen over robots because a wheel hub is round and repeatable, so 18 guns around a spinning hub coat spokes, rim and face in 12 seconds without programming per SKU. Powder was chosen over liquid because the OEM specification is met in one coat with no VOC plant in a new factory. Circumferential, side and face gun groups were specified separately so film on the decorative face can be tuned without affecting the rim.

Scope of supply and key components

ItemSpecificationNotes
Overhead chain conveyor12 s cycle, 6,000 hubs/dayAutomatic load and unload
Rotating fixtures360° rotation through the booth
Powder booth18 guns: 12 circumferential, 4 side, 2 faceFilm 70 ± 10 μm
Curing ovenGas convection, 200 °C
PretreatmentSpray tunnel for aluminium hubs
Plant layout supportPits, steel structure and electrical coordinationMUSI engineers on site during construction

Key components

Key components are available from international brands, configurable per customer specification, so that spare parts can be sourced locally over the life of the line. Brand names below are the usual options for this type of equipment; the brands actually fitted are fixed in the contract specification.

ComponentBrands available on request
Automatic powder guns and powder feedInternational tier-one powder spray gun brands
Oven and dryer gas burnersRiello RS series, Weishaupt monarch WM-G, Baltur TBG, Honeywell Maxon OVENPAK, Eclipse
PLC and HMISiemens SIMATIC S7-1500, Mitsubishi Electric MELSEC iQ-R, Schneider Electric Modicon, OMRON NX, Rockwell Automation Allen-Bradley
Variable-frequency drivesABB ACS580, Siemens SINAMICS G120, Danfoss VLT, Schneider Electric Altivar, Yaskawa, Mitsubishi Electric
Conveyor gear motorsSEW-EURODRIVE, NORD DRIVESYSTEMS, Bonfiglioli, Siemens, Sumitomo Drive Technologies
Pretreatment pumps and chemistryGrundfos CR, KSB Etanorm, Xylem; Henkel BONDERITE, Chemetall Gardobond, PPG Zircobond, Nippon Paint
Dust collector filter cartridgesDonaldson Ultra-Web, Parker BHA, Camfil, MANN+HUMMEL
Sensors and temperature controllersSICK, Pepperl+Fuchs, OMRON E5CC, Honeywell UDC, Yokogawa UT, ifm, KEYENCE

Not included in the scope of supply

  • Civil works, foundations and pits
  • Building services up to the battery limit: power supply, gas, compressed air, water and drainage
  • Local permits, emission approvals and third-party inspections
  • Paint or powder supply, unless stated in the contract

Services included with every line: engineering design, manufacturing, shipping documentation, installation supervision, commissioning, operator training, warranty and spare parts.

Typical programme

The durations below are typical for equipment of this class and are given for planning; they are not the recorded schedule of this project. A complete line usually runs 90–180 days from contract to acceptance, a single unit 30–60 days.

StageTypical durationWhat happens
Site survey and workpiece review5–10 daysRemote review of drawings and photos, or an engineer visit
Layout and detail design15–30 daysLayout drawing, utilities list and specification sign-off
Manufacturing45–90 daysBooths, ovens, conveyor, pretreatment and controls built and pre-assembled at the works
Shipping20–45 daysSea freight; equipment shipped in sections for on-site assembly
Installation15–40 daysMUSI supervision with the client's installation crew or MUSI crew
Commissioning, training and acceptance7–15 daysTrial runs on the client's parts, operator training, acceptance record

Results: before and after

Figures are those published on this page; measurement party, sample size, test date and method are not on record here and are left blank rather than estimated.

MetricBeforeAfterChangeMeasured bySingle / averageSamplesTest dateMethod / instrument
Cycle time—12 s per hub—
Ramp to full capacity—6 months—
OEM audit—passed first attempt—

Applicability and limits

The 12-second cycle applies to single-colour powder on hubs within the fixture size range. Two-coat systems such as powder primer plus liquid colour and clear, or hubs outside the fixture envelope, need additional booths and a slower takt, as described in the wheel and chassis coating guide.

Results shown in this case study reflect the stated operating conditions and should not be interpreted as guaranteed performance under different feed, production, environmental, or site conditions.

After-sales and spare parts

Warranty on a MUSI coating line runs from acceptance: 12 months on the complete line excluding consumables, 36 months on critical components such as motors, drives and the PLC, and 60 months on structural parts such as steel structure, ducting and oven bodies. Failures within warranty, excluding misuse, are repaired free of charge.

Support starts remotely: the service line is staffed around the clock, a preliminary diagnosis with recommendations is given within 2 hours, and where a site visit is needed an engineer reaches any major city within 72 hours. A spare-parts inventory is held at the Changzhou headquarters with same-day shipping, and customers can keep a dedicated parts stock at MUSI for emergencies. Details are on the after-sales service page.

FAQ

How many guns does a wheel hub line need? Eighteen on this line: twelve around the circumference, four on the sides and two on the face, with the hub rotating in front of them so no spoke or window is missed.

What cycle time is possible? Twelve seconds per hub, 6,000 per day on two shifts, which gives the 2 million a year the client specified.

Does the line support IATF 16949? The line provides the logged process data, oven records and film-thickness sampling the client's IATF 16949 system needs; the OEM audit passed at the first attempt.

Why rotate the hub instead of using robots? A hub is round and repeatable, so a rotating fixture with fixed gun groups coats it in one pass with no per-SKU programming and no robot maintenance.

Did MUSI help with the new factory layout? Yes. Engineers stayed on site during construction to coordinate pits, steel structure and electrical work for the coating workshop in the 100-day delivery.

Next step: a configuration proposal for a similar line

If your parts, volumes or plant conditions are close to this project, MUSI can return a line configuration and layout proposal. To prepare it we need four things:

  • Photos and dimensions of the workpieces, with weight and material
  • Required output (pieces per hour or per day, and shifts)
  • Number of colours and how often colour changes are needed
  • Available floor space and ceiling height, with the utilities on site

Message us on WhatsApp with these details, or use the quotation form.

Provided by Lin Cong, Technical Director, MUSI Technology · Published 2026-05-02 · Updated 2026-09-30 · Last technical review: 2026-09-30

Q

Questions buyers ask before ordering

quotation · price · lead time · installation · warranty

What information do you need to prepare a quotation?

Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.

How much does this equipment cost?

Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our complete coating line cost guide; a configured quotation is prepared from your part data. Published indicative ex-works ranges: a complete powder coating line is roughly USD 75,000–230,000 semi-automatic, USD 200,000–600,000 for a standard automatic line and USD 600,000–2,000,000 for a high-throughput automated plant.

What is the lead time?

Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.

Do you install and train operators overseas?

Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.

What warranty and after-sales support are included?

12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.

Can the environmental equipment be supplied with the line?

Yes. VOC treatment (RTO, RCO, activated carbon, zeolite rotor), dust collection and paint wastewater treatment are supplied with the coating line under one contract; MUSI has equipped 50+ coating facilities whose projects all passed local environmental compliance reviews.