Installing a Telescopic Spray Booth: Rails, Floor, Power and Exhaust Stack
Quick answer: A telescopic booth needs two levelled rails on a flat floor, a base for the fan and treatment unit at the fixed end, a duct route to a 15 m stack, and a three-phase supply for a 45-110 kW installation. Installation of a 20 m booth takes about one to two weeks after the rails are set, followed by commissioning of the drives, lighting, fan and treatment unit.

Rails and floor
Large booths run on 12 kg/m light rail laid in pairs on a levelled strip; small booths use 20 x 40 mm flat bar fixed to the floor. Rail levelling is the one civil item that decides whether the booth travels smoothly, so it is done by the site to our drawing before the frames arrive, and it is excluded from our scope. The floor between the rails carries the workpiece stands and should be flat enough for the fabric skirt to seal.
Fixed end and ducting
The dry filter cabinet or oil-film units, the exhaust fan on anti-vibration mounts and the carbon, UV or RCO unit stand at the fixed end on a concrete base. Galvanised ducting of 1.0 mm steel with angle-flange joints runs at 12 m/s or less to a stack 15 m above ground with a rain cap; a guyed steel stack is standard. Stack height follows the local rule.
Power and control
Typical installed loads: 75 kW fan, 2 x 1.5 kW drives, 30 kW UV unit and about 1 kW lighting for a 20 m booth (109 kW); or a 45 kW RCO fan with a 60 kW start-up heater for a 12 m oil-film booth. The control cabinet is installed outside the painting zone with two-station control, and the fan is started star-delta or by VFD.
| Item | Responsibility | Note |
|---|---|---|
| Rails | site (levelling to drawing) | we supply rail, site lays and levels |
| Fan and treatment base | site | concrete pad to our loads |
| Stack | MUSI | 15 m guyed, or to local rule |
| Power to cabinet | site | 3-phase, sized to installed kW |
| Lifting on site | site | crane for frames and units |
| Third-party emission test | site | after commissioning |
Installation sequence
Rails checked for level and gauge; fixed end frame and filter cabinet erected; travelling frames assembled on the rails and linked; fabric hung and fold guards fitted; drives, limit switches and stop blocks aligned; lighting and cabling installed; fan, duct and stack erected; treatment unit connected. Commissioning checks travel in both directions with both limit switches, the interlock between drives, cross-draft velocity at 0.3 m/s or more, lighting level of 300 lux or more, noise and, with the treatment unit, inlet and outlet sampling.
FAQ
How long from order to painting? Manufacture typically 30-60 days, installation one to two weeks, commissioning a few days.
Can the booth go on an existing floor? Yes, if it is flat and can carry the rails and frames; the rails are levelled with shims.
Who supplies the crane for installation? The site; the frames and units are lifted with the bay crane.
Is training included? Yes, operators are trained at commissioning on travel, filter change and fan operation.
Where MUSI Technology fits
MUSI provides the foundation and rail drawings with the order, installs and commissions on site, and hands over the operating and maintenance manual with the emission test report. Product details, typical sizes and the quotation checklist are on the telescopic mobile spray booth page.
Provided by Lin Cong, Technical Director, MUSI Technology
Send us your part size, throughput and coating type — our engineers reply within 24 hours, and a layout and budget follow once your part data is complete. Contact MUSI Technology or browse our equipment range.
Related technical guides
- Sandblasting & Shot Peening Equipment Guide 2026
Compare rotary table, hook type, tumble belt and roller conveyor blast machines: working principle, specifications, applications and cost ranges. - Powder Coating Line Site Preparation Checklist (2026)
What to have ready before a powder line is installed: foundations, clear height, power, gas, ISO 8573-1 compressed air, drains, permits and operators. - Powder Curing Oven: Gas vs Electric vs Infrared
A powder curing oven holds parts at 180-200 C for 10-20 minutes. Gas, electric and infrared ovens compared on energy cost per part, heat-up time,. - Coating Line Conveyor Types Compared (2026)
Overhead chain, floor belt, power-and-free and inverted conveyors compared on part weight, throughput, buffering, floor space and 2026 cost per metre. - Coating Line Wastewater Treatment: Process & Cost
Pretreatment lines discharge phosphates, heavy metals and surfactants. Coagulation, flocculation, sedimentation and filtration explained, with sludge.
QQuestions buyers ask before ordering
quotation · price · lead time · installation · warranty
What information do you need to prepare a quotation?
Send part drawings or photos, the largest part size and weight, the material, the required output per shift, the paint or powder type and number of colours, and the available floor space, ceiling height and power or gas supply. MUSI engineers reply within 24 hours; a recommended configuration and quotation follow once your part data is complete.
How much does this equipment cost?
Budget depends on part size, throughput and the level of automation. Indicative ex-works ranges are published in our liquid spray line cost guide; a configured quotation is prepared from your part data. Published indicative ranges: compact manual liquid spray booths from around USD 15,000–40,000, semi-automatic lines with conveyor and flash-off/curing ovens roughly USD 80,000–400,000, and fully automatic multi-colour electrostatic lines from USD 400,000 to several million dollars.
What is the lead time?
Standard configurations ship in 30–60 days from contract signing and down payment; custom configurations take longer. The delivery date is fixed in the contract.
Do you install and train operators overseas?
Yes. MUSI engineers carry out on-site installation and commissioning and give 3–5 days of operator and maintenance training. MUSI has delivered 800+ coating lines to customers in 36 countries.
What warranty and after-sales support are included?
12 months full-machine warranty, 36 months on critical components and up to 60 months on structural parts. International customers get 24-hour phone response and 72-hour on-site arrival; spare parts ship from the Changzhou headquarters.
Can the environmental equipment be supplied with the line?
Yes. VOC treatment (RTO, RCO, activated carbon, zeolite rotor), dust collection and paint wastewater treatment are supplied with the coating line under one contract; MUSI has equipped 50+ coating facilities whose projects all passed local environmental compliance reviews.